Construction is ahead of schedule at one Interstate 79 interchange in Washington County, but work on another project has fallen nearly a year behind.

Thanks to good weather, work is slightly ahead of schedule on the $35.2 million contract to rebuild the south junction of I-79 and I-70 in South Strabane, said Scott Faieta, assistant construction engineer for the Pennsylvania Department of Transportation.

But a long-awaited project to complete the I-79 Meadow Lands interchange is expected to take two more construction seasons, with completion now projected for November 2013. The project was contracted at $22.8 million with an original completion date of December of this year. The cost is expected to grow because of the delay, he said.

Mr. Faieta blamed the delay on Verizon, saying the company has been slow to relocate phone lines. "I keep hearing 'next month,' 'next week,' " he said.

Advertise with us

Verizon spokesman Lee Gierczynski said there was a delay in December because copper cable was damaged during delivery to the job site and it had to be reordered. He estimated the delay at four to six weeks. He said the company's relocation of its underground lines will be completed next month.

Swank Associated Companies Inc. of New Kensington has the contract to construct two new ramps and other improvements at what has essentially been half an interchange since I-79 was built in the 1960s.

The project will add a southbound exit ramp from I-79 to Manifold Road, Locust Avenue and Pike Street and an on-ramp from those roads to the northbound side of the highway. Traffic signals will be added at four ramp intersections and new lighting installed.

Since last spring, when the project began, the two existing ramps at the interchange have been closed, along with parts of Manifold, Locust and Pike. Two lanes of traffic are being maintained on I-79 during peak periods, with lane closures mostly at night.

The I-79/I-70 south junction is notorious for the rumble strips that were installed to slow northbound I-79 traffic as it descends a steep hill toward a sharply curving ramp to I-70, and for the scraped-up concrete barrier that keeps trucks from overturning or crashing into oncoming traffic on an adjacent ramp.

The project calls for a flyover ramp from northbound I-79 to westbound I-70 and other major improvements. Traffic restrictions will occur mostly at night, but there may be a need for ramp detours or full weekend closures later in the project, Mr. Faieta said. It is scheduled for completion in October 2014.