Work related to a $3.15 million reconstruction of a half-mile section of Castle Shannon Boulevard in Mt. Lebanon will begin in January, the Pennsylvania Department of Transportation said.
The project is one of several made possible by Act 89, the transportation funding law that the Legislature and Gov. Tom Corbett approved a year ago.
The project will rebuild the boulevard from Washington Road to Scott Road.
Dan Cessna, PennDOT district executive, said the first part of the project will be excavation by water and gas companies to replace the lines that run beneath the pavement.
That work will cause alternating one-way traffic controlled by flaggers, he said. Measures will be implemented to reduce the traffic impacts during peak hours.
About 5,800 vehicles use the street on a typical day.
When the utility lines have been replaced, temporary pavement will be installed using a cold-mix asphalt until the permanent pavement can be applied. While much of that section of the boulevard is paved with brick, the rebuilt street will be paved with asphalt, Mr. Cessna said.
“That’s a very high-volume road to have a brick surface on,” he said.
PennDOT will work with the municipality on measures to mitigate the loss of the brick surface because about half of the street is in a historic district. One of the possibilities is using brick in the crosswalks, he said.
The project will be done in phases throughout next year, to avoid having construction occur near Mellon Middle School while it is in session. As the project progresses, there will be three weekend closures and one overnight closure with traffic detoured.
Besides resurfacing the street, which originally was constructed in 1926, the project calls for signal and curb replacement and drainage improvements, including 11 new stormwater inlets designed to address flooding that occurs during storms. The new road surface will be sloped to direct surface water to the curb and prevent ponding.
“The public told us it was not uncommon to have four or five inches of water running down the shoulders during heavy rain,” Mr. Cessna said.
Completion of the project is expected by the end of October, he said.