When engineers began looking at a sewer overflow near Hazelwood about 18 months ago, they didn’t know how old it was until they found 1892 stamped into the stone of the facility where it empties into the Monongahela River.
After a process that involved finding 130-year-old construction plans, having a University of Iowa team build a scale model of the culvert and nearly a year of delicate construction managed around the weather, Pittsburgh Water and Sewer Authority and the Allegheny County Sanitary Authority showed off the new facility during a boat tour on Monday.
The $4.7 million project was designed to update a 410-foot section of the combined sanitary and storm sewer outfall system known as M-29 between Second Avenue in Hazelwood and the Monongahela River. Since that is one of more than 100 outfalls on the Monongahela alone, it highlights the massive scope of sewer improvement work facing the agencies over the next decade to improve the function of a system that also includes the Allegheny River and a small portion of the Ohio north of the Alcosan sewage treatment plant in Pittsburgh’s Woods Run neighborhood.
“The culvert itself was about 130 years old and in disrepair,” said Meghan Simek, PWSA’s project manager, including many missing bricks, holes and other problems from 130 years of wear. “If it were to fail, it would have been catastrophic.”
Here’s how the system is supposed to work: The sewer system on Second Avenue collects stormwater and sewage from the Four Mile Run watershed that includes Oakland, Squirrel Hill, Hazelwood and the Greenfield area below Schenley Park known as “The Run.”
When the water reaches a certain level, it is diverted to the outflow and dumped into the river, including untreated sewage.
Read More
Until now, that outflow had nothing to prevent river water from flowing back into the culvert. Backflow from that outfall alone can force as much as 60 million of gallons of water a year into the Alcosan system, overwhelming the treatment plant with water that doesn’t need to be treated and forcing the release of untreated sewage.
If the culvert would have collapsed, most of that overflow would have been kept in the main sewer and forced through the treatment plant.
The project, completed June, included relining the culvert by spraying on a 4-inch layer of a cement-like sealant gunite, rebuilding the endwall at the river opening and installing a 4,200-pound flap gate that covers the opening to prevent backflow from the river and opens to allow overflow from Second Avenue.
The construction was anything but simple.
At the endwall, crews for Allison Park Contractors first had to build a cofferdam around the area to create a dry space for the workers. While some were inside the culvert, one was assigned to be a “weather watcher” outside because if moderate rain occurred engineers estimated workers would have about 10 minutes to escape before they were at risk of being washed away by an overflow in the system.
To test whether the flap gate would work properly to let out water at the appropriate times, the agencies worked with the University of Iowa. The university built a 1/10th scale model to confirm that the weight of the water would force open the gate and then close it again when the overflow ended to prevent backflow from the river.
Convinced it would work, crews used a crane to lower the 15-by-11½-foot flap gate into place from the riverbank above the endwall.
Will Pickering, CEO of PWSA, stressed that the M-29 project is only a small part of the region’s federally mandated effort to sharply reduce or eliminate the release of untreated sewage. In fact, that outflow will still release untreated sewage.
Over the next 15 years, the two agencies will complete dozens of other projects, including building massive tunnels in areas such as Washington Boulevard and under the banks of the Ohio River to hold millions of gallons of material temporarily during wet periods until it can be safely treated when the weather improves.
Additionally, crews will make similar changes at other outflows. Not every outflow will have to be reconstructed, Mr. Pickering said, but the agencies will determine which ones generate the most overflows and fix them.
“We will be making massive investments in our system,” Mr. Pickering said. “We are not done investing in improving the water health of this region.”
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.