The 10th Street Bypass in Downtown Pittsburgh is closed Friday due to flooding.
PennDOT said Thursday evening that it closed the 10th Street Bypass between Interstate 279 Parkway North/Fort Duquesne Bridge and Fort Duquesne Boulevard.
The ramps from northbound and southbound I-279 to the 10th Street Bypass also are closed.
PennDOT said all traffic will be rerouted and advised motorists to use Fort Duquesne Boulevard to detour around the closure. Motorists on I-279 should use the ramps to Fort Duquesne Boulevard, PennDOT said.
Also, the Mon Wharf parking area remains closed to commuters as floodwaters continue to slowly recede from the Downtown Pittsburgh parking area.
Additional parking is available at the First Avenue Garage and Second Avenue Plaza.
Other traffic restrictions:
HOV lanes — The High Occupancy Vehicle (HOV) lanes are closed in the northbound direction of I-279 (Parkway North) in Ohio and Ross townships and the City of Pittsburgh through March 11 as part of the $87.94 million I-279 Parkway North Improvement Project.
Commercial Street, Summerset Drive, Squirrel Hill — A portion of the streets remains closed on Monday after a landslide in the area on Friday.
Kummer Road, McCandless — Closed between Ingomar Road and Walter Road, starting at 7 a.m. Monday, March 5 until late June to install a new deck and barriers and to make substructure repairs to Pine Creek Bridge No. 8.
Traffic heading north on Kummer Road will be detoured using Ingomar Road to Pearce Mill Road to and then to McKinney Road. Traffic traveling southbound will be detoured in reverse. Pedestrians and bicyclists can continue to use Pine Creek Bridge No. 8 during the closure.
The $1 million bridge rehabilitation project is being completed by Pugliano Construction Co. Inc. of Plum.
McKnight Road — Shoulder restrictions on the McKnight Road ramp to southbound I-279 (Parkway North), weekdays from 10 a.m. to 3 p.m. through early March as crews conduct bridge work.
Leechburg Road, Lower Burrell — A lane restriction between Craigdell Road and Route 56 beginning Feb. 26 and ending May 1, from 7 a.m. to 5 p.m., weather permitting, daily for inlet and pipe replacements.
Route 19/Perry Highway — Single-lane restrictions for signal installation work in Pine and Marshall at various Route 19 intersections between Wallace Road and Freeport Road in each direction weekdays from 9 a.m. to 6 p.m. through late March.
Parkway North/I-279 — Retaining wall rehabilitation work is underway on southbound Parkway North. There will be shoulder restrictions between Venture Street (Exit 4) and East Street (Exit 2B) as needed through March. Crews from Trumbull Corp. and Lindy Paving are handling the work as part of the $87.94 million Parkway North improvement project.
Connor Road, Mt. Lebanon — Lane restrictions on Connor Road will occur between Terrace Road and Greenridge Road weekdays from 9 a.m. to 3 p.m. through mid-May for gas line in installation. Also, lane restrictions on Connor Road near the intersection with Route 19 for gas line replacement and installation work.
Elizabeth Bridge (Route 51), Elizabeth, Jefferson Hills and West Elizabeth — Single-lane restrictions in each direction weekdays from 9 a.m. to 3 p.m. through April 2018. Crews will conduct shielding and paint containment installation. Also, single-lane restrictions on Route 837 (State Street) and associated ramps.
Interstate 376 — Long-term lane restrictions on westbound Interstate 376 in Findlay between Business Loop 376 West/Moon (Exit 57) and the Airport/East PA Turnpike 576 (Exit 53) interchanges, reduced to two 11 foot-wide lanes.
Other restrictions in that area include:
▪ Intermittent single-lane restrictions eastbound (inbound) between Beaver County line and the McClaren Road (Exit 56) interchange, weekdays from 7 a.m. to 3 p.m. westbound and 9 a.m. to 5 p.m. eastbound as crews from Swank Construction begin median crossover work as part of the $66.3 million reconstruction project.