Renovating a school while it is in session can be tricky, so Mars Area officials are considering moving one of two grades out of the middle school when it is renovated next year.
The district plans $14.6 million in renovations to the 49-year-old building, which houses seventh- and eighth-graders.
Administrators presented an update to the community at a Dec. 4 board meeting.
Originally, said Superintendent Wes Shipley, they considered leaving the seventh-graders at the Centennial School for another year.
“There were a lot of negatives whenever we looked at that a little more closely,” he said, including that the middle school day is very different from the elementary schedule that Centennial students keep.
He said he now believes that a better option is moving the eighth-graders to the high school. They could be housed in one area, away from the rest of the students.
“We have the opportunity to use the area in and around the auditorium,” he said. An auxiliary gym could be used by the eighth-graders. The schedule is the same, and fewer teachers would have to move.
“In either scenario, we’re going to have an issue with teachers having to revise their curriculum,” he said. Technology education teachers, for example, could teach about manufacturing “and things that don’t need large saws and dust vacuums,” he added.
Mr. Shipley said that neither option was “set in stone” at the moment, and he plans to have a firm plan to present to the board within six weeks.
Middle school Principal Todd Kolson said he concurred with moving the eighth-graders. “I don’t think Centennial has enough space,” he said. “We need 13 solid classrooms for education alone.”
The renovation project will include some changes to the floor plan and renovations to the interior.
“The project does not entail taking a lot of walls down, does not include a lot of demolition,” said John Hays of Thomas & Williamson, the district’s construction management firm.
There will be separate areas for seventh and eighth grades, each of which will be separated further into two teams or houses. The house concept “allows for collaboration. It allows for small and large activities (within) each group. It creates better connectivity between the teachers and the students,” Mr. Shipley said.
The guidance and nurse’s offices will be moved to the front of the building near the main office, Mr. Hays said.
The technology education classroom will be expanded into existing space. The art and family and consumer science classrooms will be moved and enlarged, and classrooms will be dedicated for “maker” and robotics labs.
The project also will include the raising of the floor in the cafeteria, which has sunk over the years, and the removal of the risers in the large group instruction room, Mr. Hays said.
New lockers and wider corridors also are planned.
There will be new kitchen equipment because “probably 80 percent of what is there is original,” Mr. Hays said.
Likewise, the original roof is still on the building, but has been covered in rubber over the years. A new roof will be $1.3 million of the project cost.
Jill Swaney, district business manager, said that approximately $10 million will come from a 2018 bond issue, and the remainder held in reserve from a 2016 bond issue.
“The district has on hand sufficient funds to do this project,” she said. “There’s always hope that the bidding will come in lower than projected.”
The school board is expected to award contracts in late April, and construction should begin as soon as school ends in May. The project is scheduled to be completed next December, although Mr. Hays said that most of the messy work should be done before school starts that year.
Mr. Shipley said they will likely start school after Labor Day to give the project a good head start.
There were few questions and comments from residents at the meeting. The only concern mentioned was the logistics of housing the eighth-graders at the high school, and its effect on curriculum.
Sandy Trozzo, freelance writer: suburbanliving@post-gazette.com.