Despite objections raised by several residents and town officials, a majority of McCandless council on Monday approved an operating plan and other policies related to a new regional heritage museum.
In what became a sniping match at times, council got an earful from residents who asked them to delay action on the McCandless/Northern Allegheny Heritage Center, slated to open by May 20.
Some criticized the $596,628 cost of the building being constructed off Ingomar Road near Grubbs Road, while others said it shouldn’t open without a dedicated funding source. Right now, plans call for annual operating costs of about $27,700 to be paid by taxpayers.
“This is ridiculous. You guys said you were going to spend $100,000; it’s in your meeting minutes. It’s cost five times that amount,” said resident Cindy Walterman, citing records from a July 2014 meeting.
Officials said the preliminary costs were unknown at that time. Students from the A.W. Beattie Career Center are helping to build the museum, and an additional $180,000 worth of excavation and other in-kind work was donated, along with $62,377 in cash.
The museum will be staffed by volunteers, and council said it is establishing a fundraising committee for the project.
The museum will house a collection amassed over 20 years by local history buff Joe Bullick, who worked for the North Allegheny School District for 40 years.
The artifacts include historic pieces from the North Hills area such as black-and-white photographs, maps and yearbooks along with other memorabilia, including 20th century household items and toys. The collection needed to be moved from its current location at McKnight Elementary School due to security concerns.
Resident Rita Martin said she supported the museum but asked council to postpone a vote until a new funding source could be established.
“I believe that building libraries, museums and community centers is very important and that this museum was needed,” she said. “Mr. Bullick needed a place to put all of his wonderful things. But I also believe you were irresponsible in your handling of this project because you had no defined funding source except our general budget, which became a slush fund every time you needed more money.”
Ms. Martin also criticized council for not seeking help from neighboring communities as the project is billed as a regional asset. If the project had been done with more forethought, she said, it could have included amenities the town doesn’t have, such as a community center.
“I think the council showed an irresponsible dereliction of duty to taxpayers of McCandless in planning, funding and implementation of the project,” she said.
Resident Ken Spear urged council to put together a business plan going forward.
“It was a reactionary plan, no doubt,” town manager Toby Cordek acknowledged.
A motion by Councilwoman Kimberly Zachary to delay the project and send it back to committee failed by a 5-2 vote, with Ms. Zachary and Steven Mertz voting in favor and Gerard Aufman, Joan Powers, Gregory Walkauskas, Ralph LeDonne and William McKim dissenting.
A subsequent vote to approve the project was also passed 5-2, with Ms. Zachary and Mr. Mertz opposed.
Janice Crompton: jcrompton@post-gazette.com, 412-263-1159 or on Twitter @janicecrompton.