The Allegheny River has been reopened to river traffic near Oakmont and Harmar after crews removed some of the remnants of the old Hulton Bridge that was imploded into the water on Tuesday.
Representatives of the U.S. Army Corps of Engineers were present this morning as workers for Brayman Construction Corp. used sonar to check for any debris remaining under the water and approved reopening the river, PennDOT spokesman Steve Cowan said.
Brayman had 72 hours after the demolition to remove some of the 1,600 tons of steel from the bridge to open a 300-foot-wide channel for river traffic. The river reopened shortly after noon.
Workers have been cutting the bridge into pieces and hauling them to the Harmar side of the river for removal. Large pieces remain in the water but the center of the river is open to allow water vehicles to use it.
A wider replacement Hulton Bridge opened in October as part of the $65.7 million project.