Replacement of the Greensburg Pike Bridge over Turtle Creek, a project that had been talked about and planned for at least 14 years, culminated Friday with the opening of the $20.5 million new span.
The bridge, which connects the towns of North Versailles and Turtle Creek, opened to traffic at noon. It replaced a rusting 88-year-old span that was rated one of the worst in the state and considered one of the biggest eyesores in the eastern suburbs.
The old bridge was closed a year ago and demolished while the new structure went up beside it, forcing an average of 7,000 drivers per day on a long detour.
Allegheny County began design of a new bridge in 2000, and two years later told residents it hoped to complete the construction by 2007. Construction did not begin until 2012 and the project was further stretched out by difficulties in relocating utilities.
By the time of its demise, the old bridge had undergone several stopgap repairs to keep it open and was posted with an 11-ton weight limit, a fraction of the capacity of healthier bridges.
The new four-span, 663-foot steel girder bridge is just downstream from the old structure and was aligned to eliminate a sharp angle at the end where it intersects with Penn Avenue, Airbrake Avenue and Monroeville Avenue. It has eight-foot shoulders on both sides, where the old bridge had none.
A ribbon-cutting ceremony is planned for 11:30 a.m. Monday on the Turtle Creek side of the bridge, county spokeswoman Amie Downs said.