After more than a century, Pittsburgh's water system is receiving an upgrade — starting with construction of a modernized Highland Reservoir Pump Station.

"We stopped thinking in a forward looking way about this infrastructure, and became more caretakers than stewards of [our water] system," said Deputy Mayor Jake Pawlak, standing outside the construction site near the Highland Park Reservoir in Highland Park.

“That has changed."

Friday morning, officials from the Pittsburgh Water and Sewer Authority, as well as local and state leaders, donned hard hats and bright orange vests to tour the construction site of the pump station, which is a structure that contains pipes that carry water to service areas. According to officials, it will be the authority's first major new structure in roughly two decades.

Advertise with us

While the project started earlier this year, authority CEO Will Pickering said Friday's tour marked a new phase in the $46 million investment — building the foundation and exterior structure for the pump station, which will take a year to complete.

The modernized station — which officials anticipate will be in use by Spring 2026 — will add 56 million gallons of water to the areas in Pittsburgh its services. Residents and business owners can expect uninterrupted water flow in their sinks and showers, fewer boil water advisories, and overall better water quality, Mr. Pickering said.

"We've made tremendous progress on the pump station," he said. "It's really going to be key to ensuring continued, reliable and resilient services to our customers."

Following the project's completion, the authority will also make upgrades and improvements to two other pump stations. These and other projects will lead to the replacement of the Clearwell, a century-old, 40-million-gallon water storage and disinfection facility at the water treatment plant.

A Clearwell is a water storage structure where the final step of the water treatment process – disinfection – occurs.

Advertise with us

Dubbed the agency's Water Reliability Plan, the culmination of the forthcoming infrastructure upgrades sits at half a billion dollars, primarily shouldered by low-interest loans from the Environmental Protection Agency and the state's revolving loan fund, PENNVEST.

Last year, the federal government also provided a $52.4 million loan for three separate projects within the plan.

Rachael Beam, chief engineering officer at the authority, acknowledged that the project comes at a high price and said the agency was trying "everything" to minimize costs.

"The team works tirelessly to pursue grants and low interest loans to make [the projects] affordable as possible to our taxpayers," Ms. Beam said.

She also emphasized that the Highland pump station project has so far remained within budget, on schedule, and without safety incidents.

Advertise with us

Mr. Pawlak, a former government affairs manager at the authority, applauded the agency for ushering in a new era of water infrastructure.

"About 100 years ago, previous generations of Pittsburghers built the water pipes, tanks, reservoirs, and pump stations that we still rely on today," he said.

"Now, at the end of their useful life, [the authority] is picking up the mantle to renew and replace this essential water system for our community now and for those who come after us."