Desmond Jackson stepped out the door of his friend’s house in Uptown, on his way to his car, only to discover it — and the cars that had been parked around it — were gone.

In their place were city and water authority vehicles who’d rushed to the area early Sunday morning to contain a water main break that erupted so forcefully it caused the asphalt to buckle on Miltenberger Street between Fifth and Forbes avenues.

“I was on my way to get some breakfast and my car was gone,” said Mr. Jackson, 30, who’s in town from Virginia to visit friends. “I saw all the city trucks, and all the cars that were parked there were gone.”

The city had the cars towed to make way for repair crews, who went to work shutting off water to the broken 6-inch pipe.

Advertise with us

At first, Mr. Jackson didn’t even notice the buckled road because, he said, he’d gotten used to seeing Pittsburgh’s streets in a state of disrepair.

City officials provided him with contact information for McGann & Chester towing company, which had taken away his 2013 Kia Optima. He was told that the city would either pay for the towing or reimburse him for the charge.

“Everything else has been fine this trip,” Mr. Jackson said. “It’s a good thing I’m not in a hurry.”

The break, which occurred shortly before 9 a.m., knocked out service to five homes for hours. All received robocalls from the Pittsburgh Water and Sewer Authority about the water outage, which the agency said it expected to restore by 6 p.m. Sunday.

Temperatures overnight had plummeted into the teens, a drop that often triggers water main breaks, said Rachel Rampa, spokeswoman for PWSA.

Advertise with us

Waiting for lines to break before replacing them — an approach PWSA took for years — is considered to be the most expensive way to maintain that kind of infrastructure. In recent years, PWSA changed its approach, embarking on a far-reaching set of upgrades meant to head off breaks like the one that occurred Sunday.

During the next five years, the authority expects to spend $360 million to replace small-diameter water mains like the one beneath Mitlenberger Street. This year alone, it set aside almost $84 million for the work.

Those projects are part of a sprawling, $1.8 billion plan to shore up PWSA’s portion of Pittsburgh’s century-old water infrastructure. The nearly 1,000 miles of lines owned by PWSA serve about 83,000 customers across the city.

Tim Grant: tgrant@post-gazette.com or 412-779-5834