Oakland commuters received an early Christmas present Thursday as a key portion of Bigelow Boulevard reopened for the first time in more than a year.

The section of Bigelow between Forbes and Fifth avenues had been closed since November 2019 for a $23.7 million construction project meant to enhance pedestrian safety and accommodate all modes of transportation more efficiently.

The reopening between the Cathedral of Learning and the William Pitt Union was met with little fanfare and light traffic Thursday morning, with the universities on holiday break and the coronavirus pandemic ongoing.

“I’d like to thank the University of Pittsburgh, [Pitt] Chancellor [Patrick] Gallagher and the Oakland community for developing and implementing an improvement plan that creates a safer experience for the thousands of people who use this block of Bigelow — students, commuters, neighbors and people who work in Oakland,” Mayor Bill Peduto said in a statement.

Advertise with us

The city and university said the project created a new road design including safe, separated paths for pedestrians, cyclists and motorists and updated utility infrastructure.

The design incorporates a comprehensive, multimodal-mobility plan with expanded sidewalks and crosswalk lanes — including a relocated and raised mid-block crosswalk — improves the bus-stop area and upgrades the bike connection.

The city and Pitt said the project added new green spaces and energy efficiencies to a system that will manage rainfall through sustainable landscaping practices. Updates to water lines, chilled water supply and power distribution will support the campus master plan and benefit the community, according to the university.

Pitt funded the project through its general budget and a $1 million grant from the Pennsylvania Department of Community and Economic Development with support from state Sen. Jay Costa and state Reps. Frank Dermody and Dan Frankel.

Pitt trustees approved the project plan in June 2019, and construction began in November 2019. The project was scheduled to be completed in August, but it was delayed because of the pandemic.

Advertise with us

The city partnered with Pitt to align the work with Pittsburgh’s complete-streets policy. The Oakland Business Improvement District, Oakland Transportation Management Association, Oakland Planning and Development Corporation as well as part of the Pittsburgh Campus Master Plan process joined in the development of the plan.

Contractors and other partners included the Mascaro Construction Co. and the Pittsburgh Water and Sewer Authority.

“I am grateful to Mayor Bill Peduto and the city of Pittsburgh for their continued partnership,” Mr. Gallagher said in a statement. “The new and improved Bigelow Boulevard is safer, more accessible and set to enhance how University of Pittsburgh students, neighbors and visitors will experience Oakland for decades to come.”

Andrew Goldstein: agoldstein@post-gazette.com