The massive Downtown sinkhole that swallowed half of a Port Authority bus in October could begin to be filled in as soon as next week.

The hole on 10th Street between Liberty and Penn avenues in the city’s Cultural District has been exposed since Oct. 28.

City Council on April 28 approved the city’s half of a $536,000 cost-sharing agreement with the Pittsburgh Water and Sewer Authority to fix the site.

The PWSA’s contractor, Independent Enterprises Inc., is now expected to perform the work under an already existing contract, according to Councilwoman and PWSA board member Erika Strassburger.

Advertise with us

No exact date has been set for the construction, “but it likely won't be until sometime next week, due to weather and other factors,” said Timothy McNulty, mayoral spokesman.

City Council in January approved an $88,000 expense due to Allegheny Crane Rental for removing the bus from the sinkhole.

At that time, the city was still waiting for utility repairs to be completed.

The water authority is “still exploring the cause of the sinkhole,” said Will Pickering, PWSA spokesman.

Ashley Murray: amurray@post-gazette.com or @Ashley__Murray