After several months of "extensive geotechnical analysis," the city said it is ready to proceed with construction of a retaining wall in Spring Hill needed to remediate the effects of a landslide that occurred last year.

The city called the February 2018 slide "significant" and said $900,000 will be spent on the project to repair damage that forced the closure of Diana Street near Ives Way.

The city said work will begin with clearance of vegetation and preparation of the slope before building the wall. The work is expected to take six months.

The project is one of many the city said it dealing with in the wake of 2018's record-breaking rainfall year.

Advertise with us

"Like the $1 million response to the Greenleaf Street landslide in West End last year, this represents a significant investment in slide remediation," according to a statement from the city's Department of Mobility and Infrastructure.

It said more than $8 million will be spent in 2019 “to protect and restore public rights of way.”

The region saw several landslides and wet-weather related calamities in 2018, all of which were fueled by a record amount of precipitation that was nearly 50 percent higher than normal. The Pittsburgh area logged 57.83 inches, with year-end showers Dec. 31 dropping just enough water to clinch the local record, according to the National Weather Service in Moon.

Average precipitation is about 38 inches a year in the Pittsburgh area, where records date to the 1870s. The annual figures reflect rain, snow and other frozen moisture — had it all fallen as rain.