A multimillion-dollar project to improve water and sewer infrastructure in the Strip District will affect parking and traffic patterns for several months.

Starting in late April, the roughly $9 million effort by the Pittsburgh Water and Sewer Authority will replace more than 3,600 feet of water lines beneath Smallman Street in the area of 16th to 21st streets, said Barry King, the authority’s interim director of engineering and construction.

The project also will tackle some 4,000 feet of sewer lines, retiring a combined system and separating flow into distinct channels for storm runoff and sanitary sewage, according to PWSA. Regional officials are trying to curb combined sewer systems, which can spill raw sewage into waterways during major rainfalls.

On Smallman, Mr. King said, the old sewer runs under the landmark produce terminal. The building is in line for a multi-use redevelopment project.

Advertise with us

“It’s our goal to remove any of our infrastructure that is currently under any kind of physical infrastructure, whether it’s buildings [or] bridge abutments,” he said Friday. “We just don’t feel it’s good for emergency [scenarios] to have a fixed obstacle in our way” during such repairs.

He said the Strip District project should be complete by December. During the work, street parking on Smallman in the affected area will be suspended, and drivers will see some traffic restrictions.

PWSA spokesman Will Pickering said the authority is working with parking providers and business owners in the neighborhood to ease any logistical complications. In particular, he said, PWSA has collaborated with Buncher Group and Alco Parking to have a paid parking lot at 15th and Smallman streets available on weekends.

A community meeting on the infrastructure work is set for 6 p.m. Tuesday at Contemporary Craft, 2100 Smallman St.

Adam Smeltz: 412-263-2625, asmeltz@post-gazette.com, @asmeltz.