A massive project to rebuild West Carson Street has fallen months behind schedule because of complications with underground utilities.

The $39 million project began in August 2013 and was scheduled to be completed in August 2015, but business owners who attended a meeting last month said they were told the work was eight months behind schedule.

“The problem is that existing utilities under West Carson are in some cases 100 years old,” said Steve Cowan, spokesman for the Pennsylvania Department of Transportation.

Diagrams of the buried lines haven’t always been accurate, and “if they’re off by a little bit, that creates significant problems,” he said.

Advertise with us

“We’re not pointing any fingers at the [utility companies]. They’re doing their best,” he said.

West Carson has been closed to outbound traffic since the project began, with one lane open inbound. Besides detours and delays for motorists and buses, the construction has choked a handful of businesses along the work zone.

“It’s just been a huge, huge nightmare,” said Carol Lippert, who with her husband owns Pittsburgh Marble and Granite Co. at 2421 West Carson. The company fabricates and installs stone used to install or repair counters, fireplaces, vanities and other structures.

“We’ve definitely lost business,” she said. “We’re trying to keep the business that we have, but it’s another two years [of construction] from now that we’re looking at.”

Lou Larson, vice president and general manager of Betson Pittsburgh Distributing, 2701 West Carson, said he’ll have to relocate his vending and amusement machine company.

Advertise with us

“We can’t sustain the loss of business and profits,” he said. “The project in general has really devastated our foot traffic” and caused delays in deliveries. “My competitors absolutely love it. Their sales are going through the roof.”

Ms. Lippert and Mr. Larson said PennDOT and the contractor, Lane Construction, have cooperated with them. They understand the need to rebuild the road but said the state should compensate business owners for losses during the project.

Mr. Cowan said there are no such provisions.

“Their stance is you’re open for business,” Ms. Lippert said. “You’re not closed. I really feel like no one is looking out for the little guys.”

The business owners asked state Rep. Dan Deasy, D-Westwood, who represents the area, to look into ways to help them.

Advertise with us

“Obviously, I share in their frustration,” Mr. Deasy said. “It’s a tough situation. They want the state to hand them money, but that’s not viable. Maybe we need to work with PennDOT, with all of this new transportation money, to establish a program to help these businesses get through.”

Mr. Cowan said PennDOT has erected additional signage in the West End and McKees Rocks to guide motorists to the affected businesses. The contractor “makes accommodations for deliveries and communicates with business owners on a regular basis,” he said.

When utility work is completed, the contractor might be able to work double shifts to accelerate the project, he said.

The delay has not added to the project cost, Mr. Cowan said.

Besides replacing virtually all of the ancient utility infrastructure, the project eventually will replace crumbling pavement and retaining walls, broken sidewalks and rusted railings along the 2-mile corridor.

Advertise with us

It also calls for replacement of a 335-foot viaduct that supports the road north of the Corliss Tunnels intersection, near the Norfolk Southern railroad overpass.

When construction is completed, West Carson will have a modified traffic pattern that features one 14-foot-wide travel lane in both directions to be shared by motorists and bicyclists. The lanes will have pavement markings called “sharrows” that alert motorists to the presence of bike traffic.

There will be an additional 10-foot-wide center lane for left turns by outbound traffic.

A new 5-foot-wide sidewalk will be built on the river side of the road from the West End Bridge to the West Busway entrance. A pedestrian crossing will be installed just beyond the busway, and the sidewalk will shift to the inland side from there to Stanhope Street. The road will be built lower at the railroad overpass to increase clearance for trucks.