It's time to raise the roof on the Squirrel Hill Tunnels, a project that's going to lower the boom on motorists for the next 21/2 years.
The Pennsylvania Department of Transportation's $49.5 million rehabilitation of the 59-year-old tunnels will cause inbound lane closures starting Monday night and full weekend closures of the inbound side later this year.
PennDOT on Tuesday also announced the imminent start of projects on the Veterans Bridge, Downtown, and at the Broughton Road-Baptist Road intersection in Bethel Park.
It is the first major renovation of the tunnels in nearly 30 years, and will add an estimated 30 years to their useful life, said Dan Cessna, PennDOT district executive. All traffic restrictions are scheduled to occur at night and on weekends through the project's scheduled completion in July 2014.
PG VIDEO
"A lot of effort went into how this project is phased" to avoid restrictions during peak periods, he said.
For the foreseeable future, one inbound lane will close at 10 p.m. Mondays through Saturdays. Traffic will be restored by 5 a.m. Tuesdays through Fridays but not until 10 a.m. on Saturdays and Sundays, which could cause some problems, Mr. Cessna acknowledged.
"We would expect some Saturday morning delays. Traffic typically picks up before 10 a.m.," he said.
PennDOT frequently closes a tunnel lane to do overnight routine maintenance without a serious impact on traffic. "After 10 p.m., traffic really thins down," he said.
The bigger impact will come in late July, when the first of eight full weekend closures of the inbound tunnel is scheduled. The closures will run from Friday night to early Monday morning. Before that happens, PennDOT and the City of Pittsburgh will improve pavement on the detour route, which includes South Braddock, Forbes, Murray and Forward avenues and Beechwood Boulevard.
No restrictions will occur in the outbound tunnel this year.
In addition to renovating electrical and ventilation systems, repairing concrete and tile and resurfacing the tunnel, the contractor will remove a false ceiling, raising the vertical clearance from the current 13 feet, 6 inches to 15 feet, 6 inches inbound and 14 feet, 9 inches outbound.
While the higher ceilings and better lighting might cause fewer motorists to slow down approaching the tunnels, the project isn't expected to eliminate daily backups during rush hour and at other times, Mr. Cessna said.
What it will do is reduce the number of jams caused by overheight trucks that must be stopped and turned around at the tunnel entrances. Those incidents "can make a 10-minute ride to the tunnel a 40-minute ride," he said.
The project includes rehabilitation of the Parkway East bridge over Commercial Street, which will cause four weekend closures of Commercial Street during the next two years. Dates have not been announced.
Work on the $17 million second phase of the Veterans Bridge-Crosstown Boulevard rehabilitation project will cause long-term restrictions starting next Wednesday morning. Plans call for narrowed lanes on the main span and approaches during peak periods and lane closures at night and on weekends and from 9 a.m. to 3 p.m. weekdays.
The $3.9 million Broughton-Baptist project, which calls for major improvements including new turn lanes, traffic signals and pavement, will require extensive excavation that will cause road closures starting March 26 and continuing through late November.
Eastbound Broughton Road will close from Paxton Drive to Sansue Drive; westbound Broughton will remain open. Baptist Road will be closed in both directions between Broughton Road and Higbee Drive; northbound Baptist Road will be closed between Broughton Road and Horning Road; southbound will remain open to one lane from Horning to Broughton.