The weather has warmed, daylight saving time has arrived and spring training is under way. Could construction season be far behind?
Three major bridge projects will begin in earnest this week as the Pennsylvania Department of Transportation and Allegheny County continue to assemble this year's obstacle course for motorists.
To the east, the $12.9 million replacement of the Route 30 bridges over Electric Avenue in Chalfant and North Braddock already has closed the eastbound off-ramp from Route 30 to Electric. Starting at about 9 a.m. Thursday, Route 30 traffic will be restricted to one lane in both directions as crews begin to build a crossover in the median.
When that is finished in about three weeks, eastbound traffic will cross over to the westbound side, with one-lane traffic both ways, as the eastbound bridge is demolished. The lane restrictions are expected to continue until late November.
The pattern will reverse next year as the westbound span is demolished and replaced. The bridges are 80 years old, considered structurally deficient and have sufficiency ratings of 20.7 and 32 on a 100-point scale.
Not far away, the county will begin work to replace the 87-year-old Greensburg Pike Bridge over Turtle Creek, a $16.2 million project. The contractor will build a new bridge downstream of the existing one, which will stay open with a 22-ton weight limit for much of the project. A detour will be needed when the roadway is realigned to connect to the new bridge.
The old bridge is structurally deficient and has a sufficiency rating of just 4. The county made stopgap repairs to the span in 2010 to keep it open until the new bridge is completed.
As part of the project, at 7 a.m. today, First Street in North Versailles will close and drivers will face a three-mile detour via Greensburg Pike, Warren Drive, Route 30, Navy-Marine Corps Way, East Pittsburgh-McKeesport Boulevard and Versailles Avenue. The project is scheduled for completion in late fall 2013.
In the south, a PennDOT contractor will start work on a $5.6 million bridge replacement on Curry Hollow Road in Pleasant Hills. Starting Wednesday and continuing until March 23, short-term lane closures are possible from 9 a.m. to 3 p.m. on weekdays at the bridge, which is between Route 51 and Brownsville Road near the Sheetz convenience store.
After that, traffic will be restricted to one 10-foot-wide lane in both directions around-the-clock through late November. The two-season project also will widen the roadway to add a turning lane.
The existing bridge is 73 years old and structurally deficient with a sufficiency rating of 32.
This story was originally published with images that are no longer available.