Montour Trail engineers Bill Armstrong and Mark Blum arrived at the eastern portal of the Greer Tunnel in Peters on March 21 to gather information for an interior improvement project and suddenly found themselves with an exterior project that had to take priority.
A horizontal crack across the concrete front of the tunnel – the portal – that had been there for some time looked different. It was. The hill behind it had pushed it forward, but by how much? They returned the following day with a ladder and found out – an inch and a half. Not much but not good.
“The tunnel was no longer holding the wall up as it was not (steel) reinforced concrete,” said Mr. Armstrong, an engineer with WEC Engineers of Bridgeville. He emailed Nick Koman, an engineer and trail member who is the volunteer project manager of the Greer Tunnel Rehabilitation Project. Armstrong recommended the tunnel, named in 1922 for a local landowner, be closed “until we get this resolved.”
What happened next was an example of the capability of the trail’s volunteer membership.
“My email was sent at the end of the day (March 22),” Mr. Armstrong said. “The next morning a group of Montour Trail volunteers had the tunnel closed. The (Montour Trail Council) is the model for all volunteer organizations to strive to. They are loaded with good people who take their volunteer work seriously.”
The next goal was to secure the destabilized portal façade and reopen by Memorial Day.
Montour Trail Council President Ned Williams, of Washington, Pa., wrote in its newsletter that “the prompt and robust response from the trail leaders, Cecil and Peters Friends of the Trail groups, MT’s volunteer maintenance crew and a quickly assembled team of engineers and professionals worked together to design and install an emergency fix, getting the trail back open in mid-May. Engineers drilled 25- to 35-feet from the side and top of the portal into bedrock behind the portal, inserted threaded steel rods that fastened to steel plates, and then grouted the holes.” A new portal will be affixed to the old one.
It was a costly project -- $100,000.

The tunnel remained open until July 17, when Swank Construction of New Kensington began installing a permanent steel ceiling-liner system. The company’s name may be familiar. PennDOT chose Swank as the contractor to build a new Fern Hollow Bridge after the old one collapsed Jan. 28, 2022.
The Greer Tunnel ceiling has been slowly deteriorating and parts have been succumbing to gravity. Trail volunteers erected a temporary scaffold-and-plywood shield to safeguard bicyclists and walkers from the descending debris. Mr. Williams said the lining system that utilizes steel arches and customized steel panels will stabilize the rehabilitated area, improve safety and is anticipated to last 50 years.
“We’re moving right along,” said Swank superintendent Greg Glenn one day last week. “We poured another set of concrete footers this morning.”
The footers at the base of the tunnel walls are two feet wide and four feet deep. Because of weight restrictions on a small bridge leading to the tunnel, Swank uses self-propelled buggies to carry concrete from the delivery truck to the footers and dump it into the wooden framework spiked with green-coated steel reinforcing rods.
Mr. Glenn, 65, who oversaw the Fern Hollow Bridge project, is in his 46th year with Swank. He started working at the company with his late father, Clair. His son, Dave, was inside the tunnel power-washing the walls. A four-person crew was recycling wood panels used to frame cement.
Mr. Koman, the trail’s project manager for the tunnel, said trail users “as a whole have been very supportive of the project. They understand why the trail is closed and are looking forward to having it reopened.”
Project completion date is mid-November. The trail annually attracts more then 400,000 users, primarily bicyclists.
The trail, which extends from Coraopolis to Clairton, is named for the Montour Railroad that served a number of coal mines.
In 2022, the Montour Trail Council received $240,000 in grants for the ceiling work, with the condition that it contribute $250,000 toward the project. The unexpected portal project added another $100,000. The council has launched a fund-raising campaign (www.montourtrail.org), and all donations are tax-deductible.
For now, the trail is closed off with fencing from the Chartiers Creek end of the tunnel to the Linwood trailhead parking area. Mr. Williams said there is no recommended detour around the tunnel, explaining that “nearby roads are hilly, narrow, and heavily trafficked; line-of-sight visibility is poor.”