The Montour Trail Council continues to overcome a number of obstacles as it builds the 46-mile Montour Trail from Moon Township near Coraopolis to Clairton.
So where does the 506-foot Library Viaduct rank among all those obstacles?
“It was really the ‘Big Savage Tunnel’ of the Montour Trail,” said council President Ned Williams, referring to the renovation of the 3,294-foot tunnel in southern Somerset County that enabled the Great Allegheny Passage to extend into Maryland.
The viaduct was “the outsized elephant in the living room,” he added. “It was that project that was so long-standing, so challenging, so costly ($2.4 million) [but] such a critical missing link that we really had to step up our game to get it done.”
And, as of April 30, it was done, thanks to the concerted efforts of Thornbury Inc.
Williams said the rehabilitation of the viaduct “stands as a testament to the folks who founded the Montour Trail Council [and] who believed that a complete trail was possible. Back then, such a notion was a pretty big leap of faith.”
Problems began to evaporate as municipal officials and their road crews, public works employees and park personnel pitched in, but there are still more obstacles to overcome.
The trail leading to the viaduct from the west needs to have a ride-able surface, and the trail linking the east end of the viaduct to Pleasant Street needs to be completed.
The work on the west side of the span is an all-volunteer project that began this spring. It was delayed by a leak in a 48-inch Pennsylvania American Water Company main that runs under the trail at Milepost 34.7, just east of Church Hill Road.
“The water company did a fine job of fixing the shoulders and resurfacing the trail in that area,” Williams said.
He said volunteers are back at work, cleaning out drainage ditches and resurfacing the crushed stone trail from the viaduct all the way up to the asphalt paved section near the horse farm in Peters Township.
“We hope to complete this in a month or so,” Williams said.
He said the council plans to hire a contractor later this year to work on the 943-foot segment of the trail from the east end of the viaduct to Pleasant Street and possibly complete it by the end of the year. Meanwhile, bicyclists are advised to walk their bikes over it because it’s “pretty rough.”
Williams said bicyclists can park their cars and pickups at a small parking lot at Stewart Road, about a mile east of the viaduct, or at Brownsville Extension Road, about 1.5 miles east of the span.
“We’re working on Library parking,” he added.
I suggest parking at or near the Clairton end of the Montour Trail and pedaling 12 miles up to the viaduct
“Surprisingly, it is one of the most sylvan sections of the Montour Trail,” Williams said. “Most of the route is in the valleys of Piney Fork and Peters Creek. Its character is heavily wooded, shady and close to the creek with lots of wildlife. Only the mile around the Route 51 crossing is busy; the rest is quite rural.”
The Montour Council, an all-volunteer organization, was founded in 1989 to convert the abandoned Montour Railroad right-of-way into a multi-use recreational trail for non-motorized activity for all ages and abilities. Multiple segments totaling more than 40 miles are completed, but a few gaps exist in its southern sections.
Information: www.montourtrail.org
Larry Walsh writes about recreational bicycling for the Post-Gazette.