The Pennsylvania Department of Transportation's $52.6 million makeover of the West End Circle has won an award as one of the nation's top projects, but there's some unfinished business.
An unused railroad trestle over a ramp that connects Steuben and South Main streets has forced the department to keep one lane of the ramp closed, backing up traffic and riling drivers.
PennDOT spokesman Jim Struzzi said the lane has remained closed because of concerns that trucks will take a turn too sharply and get wedged under the lower part of the railroad bridge.
The department is negotiating with Wheeling & Lake Erie Railway to acquire the trestle and remove it, he said.
"We understand the public perception and frustration with the closed lane in the West End, but we cannot allow large trucks to risk hitting the railroad overpass," Mr. Struzzi said. "PennDOT continues to press forward in efforts to expedite the purchase and ultimately remove the railroad overpass."
William A. Callison, president of Wheeling & Lake Erie, said the 2-mile spur that includes the trestle hasn't had train traffic for more than two years, and the railroad is eager to sell it. But the chairman of a real estate investment trust that has an interest in the property must sign off, and hasn't, he said.
"We've never gotten a clear answer as to why he has refused," Mr. Callison said. "We'd love to be rid of our obligations [to maintain] the branch."
David H. Lesser, chairman of the real estate trust, which grew out of the old Pittsburgh and West Virginia Railway, could not be reached for comment.
PennDOT District 11 Executive Dan Cessna said the railroad bridge could not be acquired as part of the construction project. "This was in part due to the fact we likely could have never come to agreement on the purchase in time to advance the project. And our current delays in completing this purchase only confirms that our concerns were correct," he said.
As it was, the West End makeover, which untangled one of the city's worst and most confusing bottlenecks, was delayed for several years by a lack of adequate funding. Construction began in 2007 and wasn't completed until last year.
While the project was under way, the railroad shifted its freight traffic away from the corridor on which the trestle is located and PennDOT began talks to acquire that section of line, Mr. Struzzi said.
He said there was no consideration for now of opening the ramp lane with a "no trucks" provision.
During evening rush hours, traffic on South Main and Steuben streets backs up through the West End and into the adjoining Elliott neighborhood, taking some of the luster off of the circle project, which has improved traffic flow in other directions.
"For those drivers coming across the West End Bridge straight to [Route] 51 and vice versa, it is a definite improvement, a straight shot. If you're coming from the West End on Main Street or Steuben Street, it's a different story," said Barbara Brooks of Crafton, in an email.
The project was honored this week as part of America's Transportation Awards, an annual competition co-sponsored by AAA, the U.S. Chamber of Commerce and the American Association of State Highway and Transportation Officials.
Judges said that before the project, the West End Circle "was arguably one of the most confusing interchanges in the city."
"The Pennsylvania Department of Transportation awarded the construction contract for $53 million and construction began in July 2007 to untangle this interchange, improve safety, enhance roadway continuity, improve access to the North Shore and revitalize the West End community. Project partnering, schedule monitoring and public relations and involvement ensured the project ran smoothly and without delays, while staying on budget and minimizing impacts," they said.