Cheryl Schneider’s American flag waves over the former Misty Hollow Farm in Butler County like a sentinel.
Getting to her house on Timber Lane is like a foray into another world — winding roads embraced by tree canopies on either side, a trip so quiet the only things heard are the chirps of bugs and birds, the occasional lawnmower and the sound of your own wheels.
On a recent fall day, Schneider stood in her backyard and looked out over the valley, which had once been a hill before it was strip-mined into the grassy expanse it is today. Her property and three others dot the outskirts of the valley; other neighbors look down on the field from homes atop surrounding ridges.
When the sun sets, Misty Hollow becomes a living painting and, yes — misty. Schneider likes to sit and watch the deer from under her deck.
But it’s also a flood zone — and the last place Schneider and her neighbors expected to fight a proposed data center. She worries the deer won’t come back, and that her five great-grandchildren won’t be able to play there if a massive structure hums in the middle of it all.
“Welcome-ish,” a wooden sign in cursive reads on her patio. “Depends on who you are.”
Read More
Schneider is not the only one finding herself in a battle against data centers.
In town halls and community centers across the country, residents are banding together to voice their opposition as tech and business leaders make their plans, anticipating the computational demand for artificial intelligence and attempting to sell their data center projects to borough councils and township residents.
As they do so, residents are pulling up chairs, drawing up signs and — regardless of political affiliation — becoming more neighborly with their neighbors.

Dozens of proposed data center projects have popped up in the last year across the commonwealth, and a slew of proposals have landed in Western Pennsylvania in just the past month. Pennsylvania in particular is targeted for data center development for its abundant access to water, electricity production, skilled labor and, in many cases, defunct brownfields.
In Forward Township earlier this month, residents showed up in the hundreds to make it clear to their planning commission that they did not want the 1-million-square-foot data center that developers are proposing in the center of the valley.
The meeting, held Oct. 1, was previously planned for late September. It had to be canceled because too many people showed up for the township hall to hold.
The meeting was moved to a maintenance shed — where the boos of residents reverberated off the walls and into the evening sky. The 200-person-capacity structure reached its limit nearly an hour before the 7 p.m. meeting began; a few hundred people who could not get in watched just outside, standing or sitting in lawn chairs and on blankets, signs clutched in hand.
In Forward, a proposal tabled
When news of the proposed data center first rolled through town, and given an extra week to prepare after the first meeting was canceled, residents quickly formed a coalition with the goal of protecting the character of their community.
One resident noted Forward Township’s Comprehensive Plan, released in 2022, citing its vision for the township in 2035 as one that “retains a rural character of wide open, productive spaces” and “low-density residential, small-scale commercial and industrial, and civic development.”
A data center, residents said, would not jibe with that description.
Seemingly everyone agreed, and so the meeting brought together young and old, blue and white collar, left and right voters, all unified in opposition to this one thing.
“At a previous township meeting a year ago, the conversation was, ‘How can we get the township together for America 250?’ ” resident Ian English recalled during public comment. “This is it. We’re united. We’re here. We’ve all stood up. You bond us all together. We’re in lockstep.
“Please, please hear us.”
Misty Hollow Energy and Data Campus would sit on approximately 274 acres in the valley, and be owned by 614 Prospect Road LLC, which developer Allen Sherwood manages. The proposal calls for Misty Hollow to host a 300-megawatt natural gas power plant on-site, which would grow to 600 megawatts in the future.

Sherwood teamed with Coraopolis-based GridSwitch Asset Management Services to develop the project that they said would operate behind the meter, separate from the electric grid, using a closed-loop cooling system (a recycled water system) infused with a glycol-solution as a coolant. A wastewater management system is also planned for the site. Sherwood said they would not pull water from the Connoquenessing Creek for any part of the project, but did not specify what the water source would be.
While Sherwood submitted the preliminary land development plans to the township in August, he said his team has been surveying the land parcel for three years.
If approved, Sherwood said phased construction would start early next year and take 18 to 24 months to complete, marking mid-2029 as the earliest operating date for the first phase.
But after the nearly four-hour meeting, the planning commission voted unanimously to table the proposal until the development team could come back with answers to dozens of unanswered questions residents posed during public comment.
The meeting was held for preliminary approval of the plans. The planning commission, an advisory body, was to vote on whether or not to recommend the project to the township supervisors.
“Let’s be clear,” Committee Chairman Steve Longwell said, “this is a multi-step process, and tonight is step one of that process.”
His call for calm landed on mostly deaf ears.
Scores of meeting attendees heckled speakers and interrupted the proceedings with deafening boos and disparaging remarks — so much so that Longwell had to say repeatedly: “Stop. Stop. Stop. Let the man speak!”
When Jason Kubiak — owner and president of South Park Township-based land planning and development consulting firm KubiTech, LLC — stepped up to present, his voice noticeably wavered as he attempted to speak through the uproars.
On a table outside with an anti-data center petition — which had reached over 2,300 signatures (and only about 3,000 people live in Forward) — multiple signs in bold text read:
“Cool, calm and collected! Screaming, cussing, name calling, disruption do not help our cause!”
‘The shape of the land matters’
Dozens of residents aired concerns about flooding, noise and pollution, all of which they said would be exacerbated by the project’s location in a valley.
“The proposed data center at Misty Hollow Farm is not being built in an isolated industrial park,” resident Lisa Knauf said. “It is being proposed in a valley, a valley that already sits between two natural gas compressor stations and a rail yard, [a landfill up the street], and now we’re being asked to consider putting a massive computer data center into that same environment.”
Knauf and others demanded independent studies to establish a baseline for metrics including air quality, given the “combined emissions” of existing infrastructure. Many residents said they were worried how the current emissions would mix with the data center’s.
“It’s a valley,” she said. “The shape of the land matters.”
Logistical concerns included fighting fires.
Forward Township does not have a dedicated fire department, and the nearest two stations are in Evans City and Connoquenessing — both volunteer departments. A fire department response to data centers requires special training, particularly to handle lithium-ion battery fires, all while maneuvering around computer equipment.
Flooding is also a reality of the valley, one residents said they fear would worsen if developers were to stabilize the strip-mined earth with a fill that would render the “natural sponge” an impervious surface, and potentially contaminate surrounding waterways and aquifers with runoff.
Billie Jo Rice has lived across the valley from the Schneiders since 1981. She grew up “running this valley,” knowing every trail and every hill. It’s where she rode her horses and where her sons ride their ATVs and dirt bikes. The night the first planning commission meeting was canceled, Rice stood on Schneider’s patio with her husband, two kids and other neighbors as they discussed the possibility of a massive structure manifesting mere yards away from where they stood.
“How can anyone live like that?” she asked. “Whether you’re for it or against it, like, who would, who could live like that?
“I don’t care if if you are the person that owns the data centers and love all this. You’re not going to live against it. It’s just not even humane to expect somebody to live like that. ... We’re not wealthy people. We’re not going to be able to pick up and go somewhere and give them the same life.”

The proposed footprint of the data center campus means she loses her driveway, Rice said. If she were forced out of her home, because of development or disasters, she said, she would have nowhere to relocate her two kids and husband.
Zach Purvis lives on one of the ridges that overlooks the valley, on a property his family has owned for 156 years.
It’s where, he said, family members have returned from WWII, from Vietnam, from Iraq and where he returned from service in Afghanistan. He pledged to fly a drone over the potential data center for hours every day, monitoring whether or not developers deliver on every promise.
Many residents couldn’t understand how sound control could be promised. The Schneiders have hosted three weddings, with two more planned — plus baby showers, bachelorette parties, baseball games and football games — all in their backyard. One time, a local father and daughter stumbled into a Schneider party because, they said, they “followed the music.” Purvis said he can hear every lyric from his house, hundreds of yards away.
At the meeting, Purvis played a humming noise at 86 decibels over a speaker to simulate the incessant noise of the data center, which he said the valley would amplify.
Other residents demanded sound studies not only of higher frequencies recorded at property lines, but analysis of low frequencies that can travel for miles, through objects, and disrupt bio-rhythms in humans and animals — specifically, the nearby great blue heron rookery, where bald eagles also nest.
“Reducing noise will be a significant part of our final design and engineering process,” Sherwood told the audience.
Developer promises to provide answers
Sherwood said he believes Misty Hollow could be “very significant” for the township and county by attracting private investment, adding to the local tax base and creating a “significant new source of power” with the potential to sell 300 megawatts back to the grid and lower bills for residents.
Attendees weren’t having it.
Resident Shelley Zoelle said if there are any benefits, “we don’t care. We don’t want them.”
Others pointed to the fact that Sherwood has never developed a data center.
“This is my first data center development, but I have more than 40 years of experience in real estate development and have also been involved in energy and infrastructure projects,” Sherwood said in a statement after the Post-Gazette requested an interview. “A project of this size is not developed by one person. We have assembled an experienced team of engineers, energy professionals, environmental consultants, attorneys and other specialists with the expertise necessary to develop a project like Misty Hollow Energy and Data Campus.
“My role is to bring that team together, move the project through the development process, and make sure we develop it responsibly and in a way that respects the surrounding community.”
Despite pledges by developers to build out data centers responsibly, opposition is only intensifying.
In a Quinnipiac University poll released Wednesday, 64% of likely voters in Pennsylvania think data centers will do more harm than good; 12% had no opinion, and only 24% of respondents said data centers will do more good than harm.
The issue could impact next month’s midterm election. This summer, Gov. Josh Shapiro released his Governor’s Responsible Infrastructure Development (GRID) standards, which call for data center developers to, among other things, create their own power rather than drawing electricity from the broader grid, and be transparent with communities about plans. Under the proposal, developers would need to acquire GRID certification to access tax benefits around equipment purchases.
State Treasurer Stacy Garrity, the Republican nominee for governor, said that’s not enough, and accused Shapiro of flip-flopping on data centers.
Both candidates originally were in favor of data center investments, but have since backed off, with Garrity now calling for a full pause in data center construction.
At the national level, President Donald Trump has consistently promoted AI data center expansion as a national security imperative and put data centers on the fast-track by cutting regulation.
Back in Forward, Sherwood insisted his team wanted to be “responsible” and “respectful of the community.”
“That’s why we’re here,” he said. “That’s why we’re going through this public process, and that’s why we’re listening to the questions and concerns we’re hearing from residents.”
“We’re not going to have every answer tonight. When we know something, we’ll let you know. When we don’t know something yet, we’ll tell you that, too,” Sherwood said. “And when the concerns are raised, we’re going to take them seriously.”
But many residents were furious with Sherwood and his team’s inability to answer even basic questions — including how many stories the facility would be, if backup generators would be diesel or battery-powered, and how the wastewater system would function in a township full of personal wells.
Frank Maisano, senior principal at Texas-based energy law firm Bracewell LLP, said the team hoped to return at the next commission meeting on Oct. 22 with answers.