In satellite images, Greene Township in Beaver County once stood out for the azure blue lake of coal waste that spanned nearly 940 acres and stretched into neighboring West Virginia.

Today, the blue in Little Blue Run is gone. It’s been capped with liner and a layer of soil. Much of it looks like any other industrial parcel.

And a New York-based renewable energy company, Desri, is developing a 1-gigawatt battery storage project on the site. It’s called Little Blue Project.

Named after what was once the largest coal ash impoundment in the U.S., Little Blue Run holds decades of waste produced at the coal-burning Bruce Mansfield power plant.

Advertise with us

Desri’s proposed project on the periphery of that capped waste is massive in its own right. A gigawatt is roughly the capacity of a new nuclear reactor. If Little Blue Project were operational today, it would be the biggest battery storage installation on the regional transmission grid operated by PJM Interconnection.

In fact, it would be bigger than the combined capacity of all battery storage projects across the 13-state footprint of the nation’s largest electricity grid.

Its developer, which spun out hedgefund D.E. Shaw, says on its website it has more than 12 GW of contracted solar, wind, and battery storage capacity across 80 projects in 22 states. A map shows none are contracted or operating in Pennsylvania.

Introducing Little Blue Project to the Pennsylvania Department of Environmental Protection last month, Desri wrote that its proposed battery installation is not tied to a specific energy producer or customer, but noted its “extensive relationships with data center developers and other large-load customers.

“It could certainly be paired with new off-site load through emerging ‘bring-your-own-generation’ and ‘bring-your-own-capacity’ constructs,” the company wrote, referencing strategies that both the state and PJM have entertained to ensure new data center development doesn’t stress the grid and burden utility ratepayers.

Advertise with us

Desri was responding to a request for information from the state. Through the DEP, Pennsylvania sought advance notice of large energy projects that might be eligible for an accelerated evaluation process proposed by PJM.

The grid operator has been looking for new mechanisms to add more power to the grid quickly amid reliability concerns and rapidly rising electricity prices. It proposed the expedited interconnection track as a way to find shovel-ready projects that could make a big dent in short order. Part of proving that shovel readiness is for developers to show they have support from host states.

The Post-Gazette obtained Desri’s project description through a Right to Know request. The company declined to comment.

Also included in the records produced by the state was a proposal by LS Power to replace certain engines at its natural gas power plant in Adams County, increasing the facility’s output by 272 megawatts.

A California-based publicly traded nuclear firm, Oklo, submitted a proposal dubbed Hazlebrook Power to bring a large energy campus to Forest Township, Luzurne County. Working in partnership with Liberty Energy, a Colorado-based fracking and Oklo investor, the project envisioned first building 500 megawatts of natural gas generation and using the customer commitments to add between 1-2 gigawatts of nuclear capacity using Oklo’s Aurora powerhouses — small modular reactors that are going through the licensing process.

Advertise with us

The project developers indicated to the Post-Gazette on Monday that they are no longer pursuing the project.

PJM’s fast track process opens next month. The grid operator will select 10 large energy projects that can show, among other criteria, that they’ll be operational in three years after PJM approval.

The timeline is ambitious.

A much smaller battery storage project in Beaver County, AES Corp.’s plan to bring 150 megawatts of battery power to an abandoned coal mine in Big Beaver Township, has been working to secure leases for months and, according to a recently released fact sheet, is expected to be operational in 2030.

In its project description, Desri indicated that it’s had “preliminary discussions with the Governor’s office about the Project and is seeking the Commonwealth’s sponsorship through this RFI.”

Advertise with us

The company also said it has met with Greene Township officials and noted that Little Blue Project compiles with a battery storage ordinance passed by the township earlier this year, which requires batteries to be sited on industrial land.

Greene Township supervisors did not answer an inquiry from the Post-Gazette.