For the past year, the five Pennsylvania Public Utility commissioners have been trying to figure out how they feel about the data center wave.

So has everyone else, from residents whose monthly utility bills have skyrocketed, to local utilities preparing for more demand than they’re used to, to economic development officials who want to balance the investment that data center developers are promising with the emerging public backlash.

All of this is happening before a single hyperscale data center has even flipped a switch in Pennsylvania.

Last week, the PUC finalized its model tariff for data centers. The document is non-binding, but as PUC Chairman Stephen DeFrank noted, the same five people who just spent a year crafting a policy they believe should be the standard in the state are also the ones who approve or deny utilities’ rate requests.

Advertise with us

The problem the PUC has sought to address is the impact of a new type of utility customer on all the others. The new customer is a large data center, with an electricity load of 50 megawatts (or a group of data centers with an aggregate load of 100 megawatts or more). These are sprawling warehouse-like buildings where energy-guzzling computers crunch and move digital data at the speed of modern life.

“To put that in perspective, the load of the City of Pittsburgh is 300 megawatts,” DeFrank said.

It’s not that data centers are new. It’s that some data centers are “very huge,” he said.

A 235-kilovolt power line towers over farm buildings — near where the local power utility plans to build a 500-kilovolt power line on towers as tall as 240 feet — on March 4, 2026, in Sugarloaf, Pa. (Marc Levy / Associated Press)

People tend to be more forgiving of restaurants than utilities. So here’s an analogy intended to put the data center issue into context:

Picture a sandwich shop whose mission is to serve every new customer who walks through the door. Until the shop fills to capacity, the cost to serve each additional customer is manageable, and the revenue these extra customers bring in will lower the cost per customer. It may even allow the restaurant to lower menu prices.

Advertise with us

But say 20 new hungry people come in every night at the same time and there are only 15 seats available. Now, to fulfill its mission of universal service, the restaurant has to expand — build an extension or move into a larger space. Those overhead costs certainly won’t be offset by the sandwiches purchased by those extra five customers. Eventually, the expansion may grow the business and yield more sales — spreading the cost of the restaurant’s overhead over many more customers. But that’s in the future. The construction period will be bumpy for both restaurant staff and its customers.

And then what happens if the restaurant expands but that group of 20 has already gotten a table at the taco joint down the street?

Like the beneficent sandwich shop, utilities are required to serve all customers in their territory. And they must post a menu of how each type of customer will be billed. Those utility menu items are called tariffs.

Wiring cables at a data center (Zed Jameson / Bloomberg News)

Here are frequently asked questions about the PUC’s data center tariff.

My electricity bill has gone up over the past year. Are data centers responsible?

“If your bill is going up, the chances are it's from data center proliferation,” DeFrank said.

Advertise with us

Even though no large-scale data center has been built in Pennsylvania, and your utility territory may never have any, the cost of electricity is determined in part at the level of the regional transmission grid. Utilities submit their forecasts of how much electricity demand they think they will have in the future to the grid operator, PJM Interconnection, and PJM orchestrates an auction to secure the power that will be needed based on those forecasts.

The potential of data centers in the future has caused forecasts being generated today to rise substantially. More expected demand plus the same supply equals higher prices.

Who is going to pay for utility upgrades needed to connect a new data center?

The model tariff says that if some kind of improvement to the network — even one that will end up benefiting other customers — would not be necessary “but for” the arrival of the data center, it will be up to the data center to cover the whole cost of that infrastructure.

Would those upgrades still be done by the utility company?

Not necessarily. Data centers have the option of hiring their own contractors to do the work.

“We recognize that this was an out-of-the-box proposal,” the PUC said.

Advertise with us

But this way, if deep-pocketed tech companies are able to get scarce materials and labor quickly to shore up the system, while sparing all other customers that cost, then it’s a worthwhile departure from the status quo, the commissioners concluded.

If data centers are driving up costs for all other customers, what is their responsibility to low-income residents?

With electricity costs rising, more residential customers may be struggling with their bills and more may qualify for assistance programs that include reduced bills, debt forgiveness and other help.

Today, the cost of that assistance is recovered from the rates of all other residential customers.

The PUC’s model tariff imposes an annual fee on data centers that will go into those customer assistance programs. The fee is $250,000 for data centers whose load is less than 75 megawatts; $400,000 for facilities between 75 and 100 megawatts, $500,000 for those between 100 and 500, and $1 million for the largest data centers, over 500 megawatts.

What if a data center project falls through, or it has to close shortly after opening?

Data centers governed by the model tariff will have to post collateral to cover the cost of improvements to the utility’s infrastructure. That collateral will be reduced as the work moves along and eventually will be refunded.

Advertise with us

Once a data center is connected to the grid, it will be charged for 80% of the energy demand that it said it would need, even if it doesn’t use it. There are also exit fees associated with early shutdown.

Will data centers be required to bring their own power?

No. The PUC weighed arguments for and against requiring data centers to build or contract with power generators, install batteries or show their operations are energy efficient.

In the end, the commission decided against it, in part because utilities are not in charge of power supply.

How would I know if a data center is looking to hook into my utility grid?

Utilities under the tariff would be required to post an anonymized list of data center requests, sorted by zip code, date, size of the energy load, and status.

When will my utility adopt this tariff?

The next time your utility files a rate case, it will present the PUC with its tariff menu, which is likely to include data centers.