As data centers continue to grow bigger on the ground and in the public imagination — reflections of a new technological age, harbingers of an energy squeeze that’s already driving up consumer prices — tech giants are buying the power of existing energy sources and trying to incentivize new ones.
On Friday, Meta Platforms announced three long-term deals to buy nuclear power.
The California-based tech giant signed a 20-year power purchase agreement with Vistra Energy, the Texas-based parent of Beaver Valley nuclear power station in Shippingport, and two other nuclear plants in Ohio.
The deal includes the output of the two Ohio plants, which have a combined capacity of more about 2.2 gigawatts, and the future 433 megawatts of capacity that will be available through planned equipment upgrades in Ohio and at Beaver Valley.
The Pennsylvania power plant is expected to see uprates of 140 megawatts added to its current 1.9 gigawatt capacity over the next nine years. As for its current operations, Vistra spokeswoman Meranda Cohn said the company has “interest from multiple parties in the existing generation capacity at Beaver Valley.”
The long horizon of the power purchase agreement gives Vistra two decades of security to invest in operations and to apply for 20-year extensions for the nuclear units’ operating licenses.
Read More
“Importantly, this commitment from Meta provides Vistra the certainty needed to invest in these plants and communities and bring new nuclear generation online for the grid — through uprates at our existing plants,” Vistra’s CEO Jim Burke said in a statement.
Meta also announced agreements with two new nuclear companies, the Bill Gates-backed TerraPower and Oklo Inc., which is aiming to build up to 1.2 gigawatts of new nuclear generation in Pike County, Ohio.
California-based Oklo said Meta will prepay for the power that Oklo intends to produce, which gives it the upfront capital to build its plant. The deal with TerraPower could see up to 2.8 gigawatts of new nuclear power built in the 2030s.
Meta striking deals
Ohio is emerging as a destination for hyperscalers — developers of very large data centers where computers packed into long warehouse buildings process huge amounts of data that power everything from defense algorithms to your Facebook feed.
Meta is building a 1-gigawatt cluster of data centers in New Albany, Ohio, which it has dubbed Prometheus. The campus is also being supplied by new natural gas infrastructure being built by Williams Corp., an Oklahoma-based midstream firm that has branched out into natural gas power generation to serve data centers.
This kind of deal is a financial arrangement, not a direct connection between a power source and a customer. Power purchase agreements are one way to secure the future cash flow of a developer that is going to invest in building or upgrading a power facility. Renewable energy projects are frequently financed in this way. But they can also be used to secure supply and a fixed price for power.
Meta struck a similar deal with Constellation Energy at a nuclear power plant in Illinois last year.
Constellation, which owns the shuttered Three Mile Island Unit 1, also signed a power purchase agreement with Microsoft to restart that reactor as part of its new Crane Energy Center.
On the level of the regional transmission grid, Beaver Valley and the other Vistra plants that are part of this latest agreement will continue to feed their electrons into the grid, while Meta will pull from the grid what it needs.
The Vistra deal, which was accompanied by statements of support from Pennsylvania’s governor and other high ranking politicians, does not meaningfully expand the energy reserves of the regional transmission grid, PJM, which has drawn the ire of those same politicians for the rise in costs over the past few years.
Those increases stem from the sudden and steep growth in projected demand for electricity driven by data centers in the short term before electricity supply can catch up.
Supporters of proposals for large users to bring their own generation — add as much as they plan to pull from it — have cautioned that power purchase agreement for existing assets are solving a different problem.
Beaver Valley’s ride
Beaver Valley’s fate has been a shadow of the tumult in the electric market over the past decade.
In 2018, the power station was marked for early retirement, and its owner, FirstEnergy Solutions, filed for bankruptcy while it appealed for federal intervention to save its coal and nuclear fleet. Electricity was cheap because natural gas was cheap (and abundant). It had become the largest source of electrons in PJM.
FirstEnergy Corp., the Akron-based parent of four Pennsylvania utilities, put its competitive generation subsidiary into Chapter 11 and vowed to focus on the revenue-guaranteed business of regulated distribution and transmission.
In 2020, Energy Harbor, the company that emerged from that bankruptcy, reversed the decision to close Beaver Valley and several other nuclear units in Ohio, which offered incentives for nuclear power. In Pennsylvania, the company cited former Gov. Tom Wolf’s plan to join the Regional Greenhouse Gas Initiative, or RGGI, as a good omen. The carbon pricing initiative would have required carbon-emitting power plants to pay a fee for their emissions, thereby giving nuclear energy a cost advantage.
Pennsylvania never joined RGGI. After years of legal battles in which opponents argued that RGGI would drive up electricity prices, and supporters said it would incentivize clean power generation, Gov. Josh Shapiro officially ended the state’s pursuit as part of a budget compromise in November. Earlier this week, the Pennsylvania Supreme Court dealt the final blow.
But its not Beaver Valley’s environmental attributes that have increased revenue and saved its fate.
It’s the fact that the regional grid now pays generators a historically high fee to be available.
According to the results of PJM’s latest capacity auction, which is meant to line up generation for the 2027/2028 year, Beaver Valley would get $230 million in those standby fees before it sells a single kilowatt of electricity. The auction prices have gone up because projected future demand is squeezing up against available supply.
Data centers are a big part of that equation. For power generators, they are also a big opportunity.
“We are living through times of massive growth, driven by electrification of the economy, driven by demand for data, standards for AI and cloud,” Sandeep Dudhwewala, Vistra’s senior vice president of corporate strategy said during a conference on AI and nuclear power in Pittsburgh last year. “We believe nuclear is going to play a really important role in making that happen.”