A key piece of the efforts to revitalize Downtown Pittsburgh is ready to get rolling.

In a 7-0 vote, city Planning Commission members cleared the way Tuesday for an overhaul of historic Market Square, a project that will restrict traffic to one side of the space, ban parking altogether, and create more room for outdoor dining.

With the approval in hand, the Pittsburgh Downtown Partnership is wasting little time to get started, hoping to have the makeover completed in time for the NFL draft in April 2026.

The PDP, which is overseeing the project, plans to start construction April 1, President and CEO Jeremy Waldrup told commission members.

Advertise with us

Work will start on the northern side of the square while the southern end will be “really unchanged” over the first 5½ months, he said. Construction will then shift to the south side, with the northern end reopening.

Mr. Waldup added that the center of the square will be closed throughout the duration of the project. He said the PDP sat down with business and property owners to explain and discuss the timeline.

In a release issued after the commission’s approval, the partnership stated that access to the square “will be carefully managed to minimize disruptions for businesses and the public” during construction.

All businesses are expected to remain open throughout the work.

Market Square last closed for reconstruction in 2010. Two businesses, the 1902 Landmark Tavern and Costanzo’s restaurant, ended up closing during the disruption, which included sidewalk and street closings. That $5 million makeover converted the city’s oldest public square into a European-style piazza.

Advertise with us

This time around, the PDP is hoping to prevent problems for businesses by replacing sidewalks and streets in phases and keeping at least part of the square open to traffic throughout the project.

“We are evaluating support for construction mitigation and will be in constant contact with businesses to determine impact,” Mr. Waldrup said.

Once completed, the overhaul, expected to cost $14 million to $16 million, will restrict vehicular traffic to the same side of the square as the Original Oyster House restaurant. No traffic will be allowed on the south side closest to Primanti’s. All parking will be eliminated.

The changes are meant to increase the amount of space available for outdoor dining by anywhere from 10 to 18 feet.

Despite the restrictions, Mr. Waldrup said all Market Square merchants should have access to a loading zone with a five- to 15-second walk of their front doors. The PDP plans to increase the number of loading zone spaces for those businesses by removing some paid parking spaces on lower Forbes Avenue adjacent to the square.

Advertise with us

The centerpiece of the remodeling will be a half-moon pergola-like structure that will occupy the east side of the square.

Dubbed the “Market Anchor,” the pavilion will be made of steel and glass and is meant to create a “focal point” within the square, said Kimberly Cooper, a director at Field Operations, a New York-based design firm involved in the renovation.

The open-air structure is a nod to the history of the square, which dates to the late 1700s and which in its early years contained a semi-circular enclosure used by vendors.

Featuring glass in hues of blue and green to symbolize the city’s three rivers and the sky, the Market Anchor will be available year-round and will support events like the farmers and holiday markets.

The overhaul also includes changes to Market Street, where the curbs will be eliminated and lighting and seating will be added to make it more pedestrian friendly. The street, a main drag into Market Square, will remain open to vehicular traffic but could close at times for special events.

Advertise with us

Also planned are medallions and interpretative elements designed to highlight historical events or features such as a Whiskey Rebellion, the 1877 railroad street, the Diamond Market, and Market Square’s role in the underground railroad.

In addition, the square’s existing Belgium block and bricks will be replaced with precast pavers in a bid to make walking easier. The rehab also includes new lighting, both in the Market Anchor and elsewhere, to enhance safety and security and to brighten the square at night.

The Market Square work is part of the nearly $600 million plan unveiled by Gov. Josh Shapiro in October to revitalize Downtown. It also was included in a series of public green space improvements announced by the Allegheny Conference on Community Development last June.

Under the original plan, traffic would have been banned entirely from the square. It was revised after square business and property owners objected.

According to the PDP, funding for the initiative is being provided by the state and a host of others, including BNY, Buchanan Ingersoll Rooney, Dollar Bank, Federated Hermes, Highmark, K&L Gates, Pitt Ohio, PNC, PPG, Reed Smith, and the wish Healthcare Foundation.