The COVID-19 pandemic has disrupted the timetable for a new office and residential development on the North Shore near PNC Park.

Continental Real Estate Companies will get until May 31 of next year to start construction of the eight-story building under a revised schedule approved Wednesday by the Pittsburgh Stadium Authority board.

The Columbus-based developer was expected to start the project this summer, according to Mary Conturo, stadium authority executive director.

But that all unraveled when the pandemic hit. The crisis “significantly impacted their ability to get leases for the office space and to sell the housing parcels and to get the financing,” she said.

Advertise with us

Continental is planning 48 condominiums and four floors of office and retail on the Gold Lot 4 site adjacent to the Hyatt Place Hotel and PNC Park.

Rather than start that building now, Continental instead is pledging to move forward with the construction of a 445-space parking garage that is designed to complement the overall development, Ms. Conturo said.

“We’ve been working with them on the designs and the progress and we think that they’re in good order to get that started,” she noted.

In addition, Continental will get until Dec. 31, 2021, to start work on the entertainment component of the project. That is to include a possible restaurant and a “Pirates Plaza” which may feature a tribute to the team’s Hall of Famers.

Despite the changes, Ms. Conturo told the board she believes the project is “staying on track.”

Advertise with us

“We think these adjustments need to be done in order to address what the impact has been with the pandemic,” she said.

Barry Ford, Continental’s president of development in Pittsburgh, said the firm should be ready to start the garage in October and have it completed in time for the start of the 2021 Steelers season.

“Given COVID and the market’s collapse, we just thought it was wise to switch the sequencing of the project to start the garage first,” he said.

Board chairman Stanley Lederman supported the extension.

“Everybody’s been dealing in good faith here,” he said. “The pandemic has thrown a monkey wrench into everything. I think it’s the right thing to do.”

Advertise with us

Nonetheless, while supporting the extension, board member Keith Reed questioned what would happen in the future if the pandemic was still raging and Continental was unable to secure leases for office space, buyers for condos or financing.

The stadium authority could be left with a freestanding parking garage, he pointed out.

In response, Mr. Lederman said the authority always had the option of not granting additional extensions and taking the land back. It then could seek out someone else to develop it.

Delays have not been unusual in the development of the land between PNC Park and Heinz Field, which now includes four office complexes, bars and restaurants, Stage AE and the Hyatt Place Hotel.