Workers are set to undertake demolition preparations April 1 for the controversial Whole Foods Market redevelopment effort in East Liberty, a lawyer confirmed Friday.

Actual demolition should follow in about three months at the remaining Penn Plaza apartment building, said attorney Jonathan Kamin, who represents Pennley Park South, an affiliate of developer LG Realty Advisors. But the timing of any new construction appears uncertain amid an ongoing court fight between his client and Pittsburgh Mayor Bill Peduto’s administration.

The parties remain locked in a legal dispute over plan approval while the last Penn Plaza tenants prepare to vacate by their Friday deadline. Mr. Kamin said he had “no idea” when new construction may start. First-phase plans include the upmarket grocer, 200 apartments and 12,000 square feet of offices.

“We have contractors ready to start” pre-demolition prep work late in the week, Mr. Kamin said. He said the group would not do full demolition “with people in the building.”

Advertise with us

As of Friday, two residents still at Penn Plaza had yet to line up their next homes, although both have been offered housing, Mr. Kamin said. A spokesman for Mr. Peduto estimated that fewer than 10 remain out of more than 200 people who lived at the complex last year.

“We are continuing to work closely with each and every resident of Penn Plaza over the coming weeks to make sure nobody falls through the cracks,” said Kevin Acklin, Mr. Peduto’s chief of staff, in an email message.

He said the city demands that no further demolition activity occur at the property “until every resident is out of the building.” Mr. Kamin has said the group suspended earlier pre-demolition efforts out of courtesy, but that no actual demolition happened at the remaining building. The developer provided moving allowances and relocation assistance under an agreement with the city.

“Nobody should be forced to live in a building undergoing demolition, especially elderly residents,” Mr. Acklin said. He called it “a basic matter of respect for the health and safety of the people who live there.”

The city filed a complaint last month seeking to halt alleged demolition activity at the Penn Plaza site and to force Pennley Park “to provide a decent, sanitary building” for remaining tenants. City officials claimed the developer engaged in demolition activity before the move-out deadline and that it failed to supply proper heating, all in violation of an earlier agreement.

Advertise with us

Mr. Kamin contested the complaint and later suggested the city is interested in “just killing this project.” The city planning commission in January rejected an amended land development plan — a flash point that remains in litigation.

“We have honored our agreements throughout,” Mr. Kamin said after a March 17 court appearance. “ ... We have met or exceeded everything that’s required. We’re just looking for a fair day in court.”

Allegheny County Common Pleas Senior Judge Joseph James requested formal legal briefs by mid-April.

In the meantime, a remaining Penn Plaza tenant, Franklin Means, 71, said he suffered through a ceiling water leak in his kitchen. He said he wasn’t sure if it was sewage or clean water seepage that cost him $350 in soaked food and utensils.

The steady drip appeared to vanish late last week following a visit from the Pittsburgh Post-Gazette, about two weeks after the problem first emerged, Mr. Means said.

Advertise with us

“I think they neglected the fact that [some] tenants are still here,” he said.

Mr. Kamin said Mr. Means failed to report the leak until it became serious and that he repeatedly impeded access to maintenance staff — an account that the tenant rejected. A lease agreement required Mr. Means to have renter’s insurance, Mr. Kamin said. He said the plumbing was fixed.

“I’m sorry that there was a leak,” Mr. Kamin said. “It could have been better handled if he had actually provided access to the property.”

Adam Smeltz: 412-263-2625, asmeltz@post-gazette.com, @asmeltz.