Allegheny County officials are confident they can come up with most of the money needed to repair a washed out Crescent Township road that is preventing the U.S. Army Corps of Engineers from repairing an unstable Ohio River lock.
But the proposed grant from the Redevelopment Authority of Allegheny County might come too late for the Corps, which has terminated a $3.1 million contract awarded last summer to fix a wall at the Dashields Lock that could tumble into the river.
A 500-foot stretch of sunken, disarrayed blacktop on McCutcheon Way has been a bone of contention between Crescent and Corps officials since heavy rains in May 2011 closed the road, which leads to the Dashields Lock and a township park.
Negotiations between the township and the federal agency since then have failed to provide a way to reopen McCutcheon, which would allow construction vehicles to get to the lock and repair it.
Allegheny County Executive Rich Fitzgerald met with township officials June 5 followed by a meeting between Corps and county officials this week. Bob Hurley, the county's deputy director for economic development, said much of the money for the project could come from a county infrastructure fund financed by state gaming money.
"Our goal, if at all possible, is to get this thing in construction this year," Mr. Hurley said. "It may only be a temporary fix, but there needs to be a long-term fix for that road."
Bill Cook, president of Crescent's board of supervisors, would like nothing more than that.
"I look forward to resolving this with the Corps and the county, and I look forward to getting the project started," Mr. Cook said.
The Corps awarded a contract to fix a lock wall at Dashields last summer. If the wall were to fall in, that would close the river to barge traffic, pushing coal and other commodities into trucks and railroads. Corps and industry officials warn that would increase traffic congestion and raise costs for shippers and consumers.
After McCutcheon closed last year, a series of testy on-again, off-again negotiations between the township and the Corps followed. The Corps tentatively had agreed to take control of the road and repair it, then turn it back over to the township when the lock project was completed. But the federal agency backed out after rains at Christmas caused further damage, raising the costs of repair.
Crescent township officials estimate it would take $250,000 to repair the road.
Last month, Crescent officials rejected a Corps proposal to fix the road in exchange for the township giving the agency the right to close the park for a bigger, longer-term project at Dashields, work the Corps said may not begin for years.
The township's decision prompted the Corps to redirect money that would have repaired McCutcheon to another high priority project down the Ohio at the Montgomery Lock and Dam near Shippingport. The agency's plans to replace steel dam gates that control the flow of the river have been crimped by limited funding, a predicament the Corps faces in maintaining an aging portfolio of about 200 locks and related dams nationwide. Similar to Dashields, many of the facilities were built during the Depression or earlier.
Corps spokesman Dan Jones said because of the federal budget process, the agency most likely will not be able to ask for money to fix the unstable Dashields Lock until it submits a budget proposal for the fiscal year beginning Oct. 1, 2014.