One lane in each direction of Route 28 was reopened through a rockfall zone in Harmar, using the northbound lanes, this afternoon. The traffic pattern is to remain in effect until further notice.
The southbound side was closed after the 3:45 a.m. incident and will remain closed not only for a clean-up but while geotechnical engineers assess the condition of the hillside that abuts the four-lane highway.
The rockslide not only shut the one southbound lane being used in a work zone, it also spilled over into one of the northbound lanes.
One boulder rolled across the highway and forced a northbound tractor-trailer to crash.
The overturned truck caused a chain-reaction crash involving several cars as drivers slammed on their brakes to avoid it.
Part of the cargo the truck was hauling spilled down the hillside onto Freeport Road, forcing officials to close one southbound lane of that highway.
The combination of the slide and the accident created miles of backups for morning commuters and buses that use those roads to get into town.
Jim Struzzi, spokesman for PennDOT, said it was unclear what caused the slide. He said workers had been repelling down that side of the cliff near the Hamar exit for the past week, trying to loosen rocks on the cliff's face. One of the bigger boulders to rumble down the side of the cliff during the slide weighed at least 40 tons, Mr. Struzzi said.
"Unfortunately, this is a fact of living in the Allegheny River Valley," said Mr. Struzzi. "We cut into the hillside and now Mother Nature wants it back."
Mr. Struzzi said crews would be evaluating the cliffside all afternoon. He said only after geological surveyors had determined that the cliff was safe would they consider reopening the southbound lane. He said the rocks were corralled into a basin that the crews repelling over the side of the cliff had set up to catch loose debris. He said the basin had done its job and corralled the rocks, but that the heaviest boulder had pushed the jersey barrier out into the middle of the open road.
Lt. Tom Dubovi, with the state police barracks in Kittanning, said the truck was hauling a mineral oil used to lubricate machines. Lt. Dubovi said the driver swerved out of the way of the falling debris, but he could not avoid a jersey barrier that was pushed out into the middle of the roadway by hundreds of tons of rocks. He said the mineral oil was water-soluble and that crews were still working to clean up the roadway and hillside over Freeport Road where portions of the trailer's haul spilled. He said the truck driver was treated for minor injuries at a hospital and released.
"People have listened and stayed away from Route 28," Lt. Dubovi said.
PennDOT is in the midst of spending $5.1 million to stabilize the hillside and shift the southbound side of the highway a full lane-width away by building a new passing lane.
A private contractor using a large bucket loader has been cleaning up the boulders, loading them into waiting tri-axle trucks.
But several of the rocks were so large that they had to be broken into smaller pieces before they could be carted off.
The new lane and stabilization work were to have been completed later this month. It's unknown how today's rockfall may set back that schedule.
More details in tomorrow's Pittsburgh Post-Gazette.