2004-5: Duke Lake dam cracks due to subsidence caused by Consol Energy’s longwall Bailey mine west of Ryerson Station State Park. Citing safety concerns, the Department of Conservation and Natural Resources drains the 62-acre lake.
2007: Consol applies for a mining permit in the Bailey Mine Eastern Expansion Area (BMEEA), a 3,175-acre coal reserve partially beneath the eastern part of Ryerson Station.
2013: Consol and DCNR settle the dam suit. Consol pays $36 million in exchange for rights to longwall mine beneath the eastern portion of Ryerson Station.
May 2014: The Department of Environmental Protection authorizes longwall mining in the BMEEA, except beneath two streams: Polen Run and Kent Run.
February 2015: DEP authorizes longwall mining in the first two panels (1L and 2L) under Polen Run.
December 2016: DEP authorizes longwall mining in the third panel (3L) beneath Polen Run and Kent Run.
January 2017: The Environmental Hearing Board grants Sierra Club and Center for Coalfield Justice an emergency injunction, stopping Consol short of Kent Run in the third panel.
August 2017: The nonprofits win an appeal against longwall mining in the first two panels under Polen Run but lose appeal against mining under twelve other streams.
Fall 2017-Winter 2018: DEP does not issue permit for mining in fourth panel (4L) under Polen Run. Consol revises its permit application for the fifth panel (5L), now predicting no impact on Polen Run.
March 7, 2018: DEP authorizes longwall mining in the fifth panel under Polen Run.
April 24, 2018: The EHB denies the nonprofits an emergency injunction against mining in fifth panel.
May 10, 2018: Consol completes mining beneath Polen Run in the fifth panel.
June 20, 2018: Consol files a motion to dismiss the appeal. The nonprofits oppose the motion.