Opponents of Sunoco Logistics' $2.5 billion Mariner 2 gas pipeline project said permit applications are incomplete, and asked the state to extend the public review and comment period for another 60 days.

John Poister, a state Department of Environmental Protection spokesman, said the requests would be reviewed along with the other comments at the hearing Thursday evening.

The DEP hearing in Youngwood, Westmoreland County, was the last of five the department has held on the pipeline project. The project involves construction of two new large pipelines, each 350 miles long, across the length of the state in 17 southern tier counties, including Washington and Westmoreland counties in southwestern Pennsylvania.

Approximately 125 people attended the hearing and 29 spoke. Nineteen of the speakers supported the project, citing jobs and economic benefits.

Advertise with us

State Rep. Eli Evanlovich, R-Murrysville, said the pipeline"makes sense" because it will create 30,000 temporary construction jobs and use 70,000 tons of domestically produced steel.

But Melissa Marshall, a member of the Mountain Watershed Association, said the organization's review of the permits found numerous deficiencies, and approval would endanger streams, wetlands, wildlife, public health and private property.

Ellen Gerhart of Huntingdon was one of several speakers who complained about Sunoco's use of eminent domain to gain access to their land for the new pipeline.

Previous hearings were held in Blair, Lebanon, Delaware and Dauphin counties. At those hearings, 104 people testified, according to the DEP, with comments divided equally for and against the project.

The project requires more than 20 state permits for erosion and sediment control, wetlands and stream encroachment and air emissions.

Advertise with us

The new lines would be used to move natural gas liquids — including valuable ethane, propane, butane and isobutane — from Marcellus and Utica shale gas fields in eastern Ohio and southwestern Pennsylvania to the company’s facility in Marcus Hook, Delaware County, near Philadelphia, for shipment to local, regional and overseas markets. The pipelines would have a capacity of 275,000 barrels per day.

Most of the new pipeline project will follow the same right-of-way corridor as Sunoco’s Mariner East 1 pipeline.

Chris Petrone, legislative director for Operationg Engineers Local 66, testified that the new pipelines would create thousands of new union jobs and help the region reach its energy production potential.

And the United Steelworkers union has testified in support of the project, which will use steel pipe rolled in the U.S. and union workers.

But a number of gas pipeline projects in the nation have run into citizen opposition because of environmental and safety concerns.

Advertise with us

In North Dakota this week, native Americans and environmental organizations stopped a the Dakota Access gas pipeline project from drilling under the Missouri River until court challenges, including an injunction request, could be heard in court Aug. 24.

The written comment period for each of 17 Chapter 105 permits allowing pipeline work in streams and wetland areas remains open through Wednesday.

The time frame for DEP decisions on the pipeline permits is “a moving target,” said DEP spokesman Neil Shader.

More information on the Mariner II project is on the DEP’s Mariner East Pipeline II webpage at: http://www.dep.pa.gov/About/Regional/SoutheastRegion/Community%20Information/Pages/Mariner-East-Pipeline-II.aspx

Don Hopey: dhopey@post-gazette.com, 412-263-1983, or on Twitter @donhopey