After three years of lawsuits and nearly $2 billion in cost overruns on the nation’s first nuclear construction projects in three decades, Westinghouse Electric Co. has worked out a deal that it hopes will hit the reset button and give the nuclear industry a chance to show it can work through problems without imploding.
The Cranberry-based nuclear engineering firm said Tuesday it will acquire the Texas-based nuclear construction company CB&I Stone and Webster Inc., which has been building Westinghouse’s AP1000 reactors in Georgia and South Carolina. The projects have been mired in years of delays and cost overruns, triggering legal battles between the partners and the utilities that commissioned them.
This deal ends the legal battles between Westinghouse, CB&I and the utilities that commissioned the plants.
The less tangible but important benefit to Westinghouse — and to the entire nuclear industry — said Westinghouse CEO Danny Roderick, will be to shift the focus away from the “cost stigma and schedule stigma and all the hype about that” and back to the technology.
Because of nuclear energy’s significant capital cost and long timeline, the industry has been struggling to compete against natural gas plants that cost much less to build and take only a few years to develop.
Mr. Roderick said the acquisition was necessary to ensure the projects hit their new targets. “I don’t think it’s a matter of fault,” he said. “We needed to be on a different path.”
CB&I said Westinghouse will pay it $229 million in the deal, which will also relieve CB&I of all legal claims over the projects.
A lot is riding on the new nuclear construction projects, such as the ones in China and in the U.S., to prove the industry can stay on budget and on schedule.
Mr. Roderick said it’s crucial that current nuclear development avoid the pattern established in the 1980s, “where everybody got in lawsuits and people started canceling projects.”
“Getting rid of these lawsuits is going be really good for the industry and really good for Westinghouse going forward,” he said.
The settlement with utilities and other project owners amends the contract governing the engineering and construction in several major ways: It limits Westinghouse’s ability to seek price increases, allows the project owners to lock in a fixed price if they choose and establishes steep penalties for Westinghouse if it misses project milestones.
It also reaffirms Toshiba, Westinghouse’s Japanese parent, as the ultimate guarantor for Westinghouse’s obligations.
“[The deal] allows us to have total control at the construction sites at Georgia and South Carolina” and expands Westinghouse’s reach into the decommission of old nuclear plants, environmental remediation and modifications to existing nuclear plants, Mr. Roderick said. CB&I was also Westinghouse’s partner in China, where the world’s first AP1000 reactors are expected to be operational starting next year.
Westinghouse said it intends to hire Fluor Corp. to manage the construction at the U.S. nuclear projects. Fluor would then hire the CB&I employees working on the two projects — between 7,500 and 8,000 workers.
The move is “a long-term play” for the company, as CB&I was going to be Westinghouse’s construction partner in other projects such as those pending in the U.K. and Turkey and possibly others in the U.S.
Westinghouse will form a new subsidiary to house its acquired assets from CB&I, which includes heavy equipment and 11 facilities in the U.S. and Asia. The new company will also include a new government services business that it is developing.
Anya Litvak: alitvak@post-gazette.com or 412-263-1455.