Shell Chemical Co. and the Center Township Water Authority have reached an agreement that will give the township a new water intake site and a new water treatment plant, with Shell footing most of the bill.
The water authority estimated the project would cost $72 million and has previously budgeted about $3 million for it. Shell has agreed to pay the rest.
The authority’s current water source is on the site that Shell has been preparing for a multibillion-dollar ethane cracker, although it has not made a final decision to go ahead with construction.
Shell mentioned moving the intake site and the need for a new water treatment plant for the authority in its lengthy soil-remediation plan, which the company estimated would cost another $80 million.
In a statement Tuesday, Shell said it was pleased to have reached the agreement, something that was necessary for the company to continue its site-preparation work.
“The next step involves pre-construction activities to build a roll-on, roll-off dock facility near where the (authority’s) water supply source is currently located,” the company said. “Pre-construction activities related to the dock are critical to the potential construction phase if Shell decides to build the facility, since it will be used to deliver major pieces of equipment. Planning to build the dock now will allow Shell to maintain its schedule for the potential construction phase.”