Regarding your editorial on the settlement agreement relative to the Liberty Bridge fire (“Pay the Fines,” July 16): PennDOT does hold contractors accountable for impacts on our projects in several ways. The circumstances surrounding the Liberty Bridge project and the impacts of the Sept. 2, 2016, fire damage are quite complex. I would like to summarize the impacts of the fire event and how things played out to drive completion of the project through safe and expedient resolution.

The fire damage required closure of the Liberty Bridge well outside of the parameters of the contract. Contractual damages for undue travel delays on the motoring public amounted to $3 million. In addition, the department expended approximately $800,000 in engineering costs to assemble a team of leading engineers from universities and consultants to address traffic flow concerns and ensure a safe resolution of the fire damage.

The contractor expended $5 million to develop jacking procedures, construct a temporary support to stabilize the structure and then make permanent repairs. The department is not reimbursing the contractor for these costs. PennDOT is requiring the contractor to reimburse us for our $800,000 expenditure referenced above.

After the bridge was reopened last year, the contractor accelerated the work with additional overtime to recover time lost during the bridge closure. This cost the contractor approximately $264,000. PennDOT did not pay the contractor anything extra for this effort.

Advertise with us

To reduce further delay impacts to motorists, the department negotiated a revised approach with the contractor. We agreed to allow closures and traffic impacts that were originally precluded by the contract, and waived further liquidated damages relative to these, to remove the traffic restrictions faster. Yes, the motorists were impacted on these days, but the total duration of impacts was reduced.

To do this work in an expedited fashion within these modified parameters, the contractor expended approximately $648,000 to accelerate their efforts to complete the traffic restrictions at the agreed pace. PennDOT did not pay the contractor anything extra for this accelerated effort.

So, to summarize, the contractor expended quite a sum to rectify the damage, and to accelerate the completion of work requiring traffic restrictions as negotiated. The concessions PennDOT yielded were intended to return full access to the bridge for regular traffic flow faster than originally planned. I hope this explains why PennDOT took this approach.

LESLIE S. RICHARDS

Secretary