Contractors began the meticulous process early Thursday of testing the system that will move the new Commercial Street Bridge into place on the Parkway East next month.
Specialty subcontractor Mammoet, a Netherlands-based company that is a world leader in moving big things, planned to move the bridge about a foot Thursday and move it back as a test run. Work started at about 6:45 a.m. and by 8:15 a.m. it had moved about three-quarters of an inch.
The work was expected to be finished on Thursday, but after extending the testing hours past 4 p.m., the state Department of Transportation stopped work about 7 p.m. However, additional testing has been scheduled for Friday and Commercial Street under the bridge will be closed again from 6 a.m. to 9 p.m. unless the work is finished earlier.
PennDOT spokeswoman Yasmeen Manyisha said crews were “making adjustments” to the slide system to make sure it works properly next month but offered no details about why more testing is needed.
The testing is being done in preparation for next month’s 25-day closure of the Parkway East beginning July 10. That’s when the old bridge will be demolished and the new span is moved into place.
Crews will use 42 hydraulic jacks to lift the new bridge about 10 inches off the ground and slide it 102 feet into place on the previous abutments.
Read More
At a news conference in Frick Park Thursday, state and local officials lauded the creative engineering that has gone into the project and told the public to plan for detours that will disrupt about 100,000 motorists every day.
PennDOT Secretary Mike Carroll called the plan to build the new bridge beside the old one and slide it into place after demolition “a stunning engineering achievement.”
“All I can think of is ‘Oh, my God, this is unbelievable,’ ’’ he said. “… This is a ‘holy cow’ moment. I can’t wait to see this bridge moved into place.”
Thursday’s test was the first and only tangible practice for moving the 22 million-pound, 846-foot-long bridge.
General contractor S&B Fay USA, which has a $95 million contract for the project, built the new bridge in the park adjacent to the old one.
After a series of meetings with residents and motorists, PennDOT decided to use the option that required a nearly monthlong full closure of the highway. The alternative would have involved about four years of traffic restrictions during construction, officials said.
PennDOT plans to close the highway at 9 p.m. on July 10. Crews will then demolish the current bridge, first removing the deck with machines and then bringing down the substructure with explosives.
After cleanup, Mammoet will move the new bridge into place at abutments on each end of the valley, where crews will attach the new bridge. Then S&B Fay will finish paving the approaches at each end of the bridge before it reopens.
The contractors can receive bonuses if they finish ahead of schedule and fines if the new bridge doesn’t open on time.
Closing the highway is expected to cause serious traffic congestion with as many as 100,000 motorists finding alternative routes. PennDOT has encouraged employers in Oakland and Downtown Pittsburgh to allow remote work.
Jason Zang, PennDOT District 11 executive, and Katharine Kelleman, executive director of Pittsburgh Regional Transit, urged the public to plan ahead and use public transit.
“If I’m here, you know what that means: Don’t drive,” Kelleman said. “It’s going to be a mess. Let us get you where you need to go.”
Kelleman said PRT will operate regular service during the project and will have additional vehicles available if buses get too crowded. Once buses from eastern suburbs get to Wilkinsburg, she noted, they can use the Martin Luther King Jr. East Busway to avoid traffic jams.
The agency won’t operate special service like it did for the NFL Draft in April, Kelleman said, because riders will be headed to a variety of locations, not a specific spot such as Downtown Pittsburgh or the North Shore during the draft.
Zang encouraged motorists who must drive in the eastern suburbs to “plan ahead,” use posted detours and follow real-time updates on traffic congestion at 511PA.com.