Pittsburgh Regional Transit expects to begin an upgrade to the poorly rated Centre Avenue Bridge over the Martin Luther King Jr. East Busway in Shadyside late this year or early next year.

Denise Ott, director of capital programs, outlined the project on the 240-foot bridge Thursday for the agency’s Performance Oversight Committee. The committee recommended awarding a $1.8 million contract for the project to Mosites Construction Co. when the board of directors meets June 26.

Ott said the project will involve a lot of substructure work, including replacing and resetting bridge bearings, new bearing supports and painting.

Mosites likely will receive permission to proceed in about two months. The work is expected to take about 11 months.

Advertise with us

Greg O’Hare, PRT’s chief engineer, said the structure near the Hillman Cancer Center was built in 1979 in anticipation of the construction of the East Busway. The busway was installed beside Norfolk Southern railroad tracks and the new bridge was needed to provide additional space to accommodate the busway underneath it.

As a result, the bridge has a complicated ownership.

PRT is responsible for the substructure and one abutment, which is what will be addressed with this project, but Pittsburgh is responsible for the bridge deck and the railroad owns the other abutment.

Ott said there will be some traffic restrictions during the project when the bridge is closed so it can be raised with jacks to replace the bearings, but the exact dates for that work haven’t been set yet.