The next phase of a major North Hills construction project will commence overnight on Wednesday, forcing the overnight closure of a stretch of the southbound lanes of the Parkway North for three nights.

Interstate 279 will be closed southbound between the Camp Horne Road exit ramp (Exit 8) and the McKnight Road entrance ramp, including the high-occupancy vehicle lanes, as crews demolish Jacks Run Bridge No. 3, which carries Jacks Run Road over the highway.

That stretch of the parkway will be closed from 9 p.m. to 5 a.m. Wednesday, Thursday and Friday. Roughly 73,000 vehicles per day travel that section of the highway, county officials said.

The I-279/I-579 HOV lanes will also close northbound at 9 p.m. Wednesday, Thursday and Friday until they reopen inbound at 6 the following mornings.

Advertise with us

When the southbound lanes are closed overnight:

• Southbound traffic will be detoured back to I-279 using Camp Horne Road, Lowries Run Road, Rochester Road, Babcock Boulevard and McKnight Road.

• Southbound traffic to Union Avenue in Ross will be detoured using Camp Horne Road, Lowries Run Road, Rochester Road, Perry Highway, Highland Avenue and Gass Road.

• Southbound traffic to Cemetery Lane in Ross will be detoured using Camp Horne Road, Lowries Run Road, Rochester Road, and Perry Highway.

The closures on the Parkway North and the HOV lanes are expected to continue through August, and the county will release new information each week.

Advertise with us

The bridge is being removed this year under a $2.8 million contract with Swank Construction Co. of New Kensington.

Why Jacks Run Bridge No. 3 is being demolished

Last summer, a contractor repairing deteriorated concrete on the span found the problem was more serious than expected. The county ordered a more extensive inspection that found corroded steel reinforcement bars, including several that were broken, leading to the closure of the bridge.

The bridge had been scheduled for replacement in 2028, but after the closure, the county reviewed whether it should repair the bridge or move straight to replacement.

After discussions with the Southwestern Pennsylvania Commission, which authorizes funding for road and bridge projects for a 10-county area, the replacement was moved up a year to 2027.

The county will advertise later this year for bids to build the replacement for the 202-foot bridge, which opened in 1986. The new bridge should be completed before the end of the 2027 construction season.

The entire project is being funded by the Federal Highway Administration, and the money is being managed by the Pennsylvania Department of Transportation.