Construction workers were putting some finishing touches on an almost 100-year-old tunnel, as both the inbound and outbound portions of a $13.1 million project were scheduled to fully reopen Thursday morning, officials announced Wednesday.
Allegheny County Executive Sara Innamorato, U.S. Rep. Summer Lee, state Sen. Wayne Fontana, county Councilman Jordan Botta and other officials cut a ribbon in the outbound portion of the project, as construction partners highlighted various improvements — fireproof wall panels, masonry cleaning at entrances and exits, lighting, electrical and fire detection and suppression system upgrades, a CCTV monitoring system, and new pavement, a curb, sidewalk, signs, and pavement markings.
Of the $13.1 million cost, 80% came from the Federal Highway Administration, and the county covered the other 20%. Of the federal dollars, $1.25 million came from the Bipartisan Infrastructure Law. Mosites Construction Company of Robinson was the rehab project’s main contractor.
Other aspects of the project include reducing the lanes in both the outbound and inbound portion of the tunnel, which opened in 1927 and is named after former county commissioner and Pittsburgh Mayor Joseph G. Armstrong. Officials said that prior to the project, there were two 10-foot-wide lanes in each tunnel with no shoulders — now, the inbound tunnel has one 12-foot lane with two 4-foot-wide shoulders except at the exit, where there are two right-turn lanes. In the outbound tunnel, there is now one 12-foot lane with roughly 3-foot shoulders except at the exit, where there is a left-turn lane and a straight/right-turn lane.
The sidewalk in the outbound tunnel was also widened from 3 feet and 9 inches wide to 6 feet and 3 inches wide throughout most of the tunnel. County officials said that the sidewalk will likely remain closed through September because of work that Duquesne University is doing on Fisher Hall pedestrian bridge, which is near the Forbes Avenue side of the tunnel.
Stephen Shanley, the county’s director of public works, said projects like the Armstrong Tunnel rehab are important for safety and general improvements, noting the last major rehab to the tunnel occurred from 1989 to 1991. The life safety and general enhancements, combined with the various contracting partners and city and state government, made it a tricky but necessary project, Mr. Shanley said. The tunnel sees more than 11,000 vehicles daily, officials said.
Read More
“It’s challenging because it’s the only tunnel we have ... we had drainage issues with the old tunnel, so tiles were popping off the side walls. And we improved the drainage in the ceiling, to make the tunnel last longer,” he said.