The Highland Park Bridge will see intermittent lane closures and more during a yearslong preservation project, officials said Wednesday.

The project is in the preliminary engineering stage, a step that is expected to be completed during the spring or summer, PennDOT District 11 Project Manager Erik Porter said during an online community meeting.

The final design stage will begin shortly thereafter and last until midway through 2027, when construction is expected to begin. Construction will be completed in 2029, he said.

The Highland Park Bridge, connecting Highland Park and Aspinwall, carries four lanes of traffic and a sidewalk over the Allegheny River, the Allegheny Valley Railroad line and Norfolk Southern Railroad line.

Advertise with us

The bridge was constructed from 1937 to 1940, with its last major rehabilitation occurring in 1984, according to Lochner Consultant Project Manager Steve Rodgers. The bridge is eligible for the National Register of Historic Places due to its technological significanceh, he said.

The proposed bridge improvements include retrofitting and repairing various steel members, repainting the bridge, replacing expansion joints and rocker bearings, fencing and drainage upgrades, and repairs for the steel and concrete substructure.

The bridge’s southern decks will be fully replaced, Mr. Rodgers said.

“These decks have served their useful life and aren’t salvageable anymore,” he said during the public meeting.

The preservation work on the bridge will require partial lane closures, lane closures with directional detours and some continuous daily closures on both weekdays and weekends, depending on the stage of the project, officials said.

Advertise with us

Rehabilitation work on the southern ramps will require full closures with detours of each ramp, but the project will generally lead to single-lane closures, said Mr. Porter.

“I don’t believe the project will be done 24/7, [but] we are looking to accelerate the construction,” he said.

PennDOT and Lochner have not yet determined how pedestrian traffic will be impacted.

During closures, drivers will detour across the 40th St. Bridge, a route that will be posted. An alternate route across 62nd St. Bridge will not be posted because it does not provide “direct and continuous” access to Route 28, said Mr. Rodgers.