Pittsburgh Regional Transit said the MLK Jr. East Busway was to reopen at 5 p.m. Friday, a week after a water main break created a landslide in Polish Hill that left nearly 6 feet of debris that closed the busway.
Crews on Friday placed 34 concrete barriers and 21 concrete blocks along the 272-foot stretch where a portion of the hillside collapsed, dumping tons of mud and trees across both lanes of the busway. A PRT release said the barriers would prevent additional debris from falling onto the busway and disrupting operations.
But buses traveling through the area will alternate using the lane farthest from the hillside, and all vehicles will be restricted to 25-miles-per-hour. Earlier the transit agency said it would be putting in a mobile traffic light that will have buses travel through the busway one at a time through the impacted area,
Additional field observations and a geotechnical assessment will help PRT determine when the busway can return to normal operations, the release said.
The landslide took away part of Brereton Street in Polish Hill and carried mud and debris down to the busway following a water main break.