Beginning Monday, the exit ramp off I-376 Parkway East in Churchill and Wilkinsburg will be closed until late August, according to the Pennsylvania Department of Transportation District 11.

A full closure of the ramp will occur from westbound I-376 to the Wilkinsburg, Route 8 North exit (exit 78B). During this time, PennDOT crews will be fully replacing and lowering the ramp.

Traffic will be detoured as follows:

Westbound on I-376 to Wilkinsburg Route 8

Advertise with us
  • Take the Churchill/Route 130 (Exit 79B) exit
  • Continue straight on William Penn Highway/Penn Avenue
  • Bear to the right onto Route 8 (Lincoln Highway/Penn Avenue)
  • End detour

Westbound on I-376 to Route 30 (Ardmore Boulevard)

  • Take the Edgewood/Swissvale (Exit 77) exit
  • Turn left on South Braddock Avenue
  • Turn right on Monongahela Avenue
  • Turn right onto the ramp to I-376 East
  • Take the Forest Hills/Route 30 (Exit 78A) exit
  • End detour

This closure is a part of PennDOT’s $95 million I-376 Commercial Street Bridge Replacement project, which is taking place between the Edgewood, Swissvale interchange (exit 77) and the Squirrel Hill Tunnel.

Crews during this time will also be working to install new overhead signage and retaining walls, and lowering the ramp to Wilkinsburg. Eventually crews will slide the new Commercial Street Bridge into place to connect the Parkway with the tunnel.

Drivers can check road and traffic conditions by visiting www.511PA.com.

Ciara McEneany: cmceneany@post-gazette.com