Pittsburgh Regional Transit has announced a slew of rehabilitation projects for the county’s light rail system.
In a news release, PRT said a multi-year rehabilitation effort will begin in April.
The region’s light rail system, called the T, includes just over 26 miles of tracks running from the North Shore, through Downtown and into the neighborhoods of the South Hills.
According to PRT, the “ambitious, multi-year rehabilitation effort” will see more than $150 million used to improve the region’s light rail infrastructure.
PRT said the effort combines multiple projects that were at first intended to be completed separately. Combining the effort will “streamline operations, maximize efficiency and minimize disruptions,” PRT said.
The projects will run one after another through 2028.
Read More
The effort includes repairs and replacements to the T’s infrastructure, including the repair of the concrete rail foundations in the Downtown tunnels, the replacement of more than 10,000 feet of light rail track and the reconstruction or upgrading of certain stations.
Another project further down on the timeline would see the rehabilitation of the Panhandle Bridge that takes light rail cars over the Monongahela River. PRT said the Panhandle Bridge hasn’t been rehabilitated in roughly 40 years.

“These projects are an important investment in our region’s future,” said PRT CEO Katharine Kelleman in Tuesday’s news release. “By fortifying our light-rail system, we’re building a stronger, safer, and more reliable foundation for years to come.”
With the undertaking comes interruptions to service — some larger than others. The first project beginning April 5 involves the Downtown subway tunnels and will see the temporary closure of the light rail system between Steel Plaza and Gateway stations.
Another closure later this summer will see essentially the entire Red Line affected.
A meeting to discuss the community impact and an overview of all projects will be held Thursday at 6:30 p.m. in Beechview at St. Catherine of Siena Church on Broadway Avenue. An online meeting will also be held April 2 at 4 p.m.
Those who want to see the meetings but can’t attend can view them afterwards online here.
PRT said many of the projects are fully funded, but it’s still seeking funding for some, such as the rehabilitations of the Station Square and Dormont Junction T stations. Those rehabilitations still have pending designs.
Here’s the list of projects.
Plinth work: April 5 to May 30
The first project in the multi-year effort will see PRT expand the repairs and replacement of the plinth in the Downtown subway tunnels. The plinth is the concrete beam which the light rail tracks sit on.
Work on the plinth started late last year and has occurred on-and-off on weekends since. Starting April 5, the work will expand to seven days a week.
During the plinth work, riders traveling to or from Gateway, North Side or Allegheny stations will be impacted. Rail cars coming from the south will serve First Avenue and Steel Plaza stations and then continue to Penn Station, which is usually inactive and is located across Dr. Martin Luther King Jr. East Busway from The Pennsylvanian. Riders can then get off at Penn Station, take a free shuttle bus to Gateway and then continue on the light rail to North Side and Allegheny stations.
Riders heading south from Gateway will need to get off the rail car at Gateway, take a shuttle bus to Penn Station and then can get back on a rail car to the South Hills.
After May 30, work will still continue on the plinth on some weekends through the summer. Another multi-week closure to complete the project is likely in 2025.
Willow Street track replacement: May 17 to June 15
Rail cars will travel on a single-track between St. Anne Station and Willow Station while the tracks on Willow Street are replaced.
Alfred Street track replacement: June 16 to July 14
Rail cars will travel on a single-track between Overbrook Junction and Dormont Junction while the tracks on Alfred Street are replaced.
Red Line closure: June 16 to Aug. 31
A major closure affecting more than a dozen stops on the Red Line will be in effect throughout the summer for several projects.
The Red Line will be closed from Overbrook Junction to South Hills Junction.
PRT said that during the closure, Red Line trips will be detoured via the Blue Line and two new temporary bus routes will be added.
The 42-Potomac will travel from Potomac Station to Station Square.
The 37-Castle Shannon will travel from Castle Shannon Station to Station Square.
In addition, a rail shuttle will operate between Dormont Junction and Overbrook Junction to let riders travel south to Overbrook Junction and transfer to the Blue Line at Willow.
Closure of Mount Washington Transit Tunnel: 2025
The Mount Washington Transit Tunnel, which buses and rail cars use to travel between the South Hills and Downtown, will be closed for several months while the rails in the tunnel are replaced.
Rail cars and buses will be detoured through Allentown. An exact timeline for the closure will be announced later this year.
Mt. Lebanon Transit Tunnel track replacement: 2026
With work expected to start in 2026, PRT said it will replace the tracks in the Mt. Lebanon Transit Tunnel.
Projects in 2026-2028
Also expected to start in 2026, PRT said the Panhandle Bridge will be rehabilitated for the first time in roughly 40 years. This project is the longest listed by PRT in the multi-year light rail effort, with work on the bridge expected to take about 30 months to complete.
Station Square and Dormont Junction will both be rehabilitated in the coming years. PRT said there is no timeline on this project yet as they aren’t fully funded, although the designs are expected to be complete by the end of this year.
PRT said it will announce each project’s full timeline, including detours and other service information, as they approach.