The Swindell Bridge, which closed July 1 after debris from it fell onto Interstate 279 underneath, will reopen to traffic Thursday afternoon, Pittsburgh’s Department of Mobility and Infrastructure announced.
But the city said crews had to cover over the problem that allowed the debris to fall rather than fix it because material isn’t available. The bridge joins the North Side’s Perry South and Northview Heights/Spring Garden neighborhoods.
Crews had been milling part of the bridge surface for temporary repairs in late June. After the debris fell July 1, an inspection determined waste material from that work built up and caused a tear in an expansion drainage trough, allowing debris to fall onto the interstate.
After waiting several weeks for material to replace the trough, the city had Allison Park Contractors weld over the damaged area so the bridge could be reopened.
“Unfortunately, we continue to have difficulties procuring a replacement due to supply chain issues,” said Maria Montano, spokeswoman for Mayor Ed Gainey. “In the interim, the contractor welded steel plates over the expansion joint to ensure no other debris can pass through to the trough below.
“The city is continuing to pursue all available avenues to source a replacement trough and anticipates having the new one in place by the end of the year.”
Read More
The temporary work is designed to keep the bridge open until a major rehabilitation project begins later this year.
The 545-foot bridge opened in 1932 and last had major work done in 1990.
The bridge has been rated in poor condition since 2009, meaning it must be inspected every six months instead of on a normal two-year cycle.
The city said the recent inspection found no additional problems with the bridge.