Parts of Grandview Avenue and Wyoming Street in Mt. Washington will be closed to traffic Tuesday to make way for construction on the Upper Station of the Monongahela Incline.

From 7 a.m. to 3 p.m., a crane hired by Pittsburgh Regional Transit will be removing a back-up generator and fuel tank connected to the station, as part of a larger set of repairs to the Incline PRT began Monday and will continue through Nov. 11. The generator and fuel tank at the Upper Station will be replaced in the coming months, according to Adam Brandolph, PRT’s public relations director.

As the contractors work, Grandview Avenue will shut down for one block, from Shiloh Street to Wyoming Street, and Wyoming Street will be closed from its Grandview Avenue intersection to East Sycamore Street.

Residents of the apartment complex and houses on the block can enter and exit the cordoned-off stretch of road throughout the day.

In the event of rain, the street closures and construction will be rescheduled for Aug. 10.