The National Transportation Safety Board’s preliminary report  Monday on the Jan. 28 Fern Hollow Bridge collapse indicates the bridge began falling from the Squirrel Hill side of the structure, but it doesn’t offer any reason why.

The report, which the agency normally releases about 10 days after a major incident, indicates the agency expects to spend more time at the Frick Park ravine where the bridge debris fell. Its full investigation could take as long as 18 months.

The investigation team, lead by NTSB Chairwoman Jennifer Homendy, has been reviewing the scene since the collapse happened. Construction crews over the weekend began lifting heavy pieces of debris so investigators could look under it for evidence.

The collapse, which occurred about 6:40 a.m., took a Port Authority bus and five other vehicles into the ravine. Ten people were injured.

Advertise with us

“Initial assessment of bridge components indicates that the collapse initiated at the west end of the structure,” the report said. “Further examination will be performed as debris from the bridge is removed and unobstructed access becomes available…

“The recovery of evidence, including extraction and documentation, is expected to be a lengthy process.”

The bridge has been listed in poor condition since 2011, with inspectors raising particular concerns about the condition of steel supports. Cables were installed on the west end, closest to Squirrel Hill, to bolster the supports.

The initial investigation found no fractures of bridge beams, the report said.

“Although certain areas of the welded steel girders were identified as being fracture critical, no primary fractures were found in these areas,” the report said.

Advertise with us

Under federal regulations, a fracture critical member is a “steel member in tension, or with a tension element, whose failure would probably cause a portion of or the entire bridge to collapse.”

The bridge, opened in 1973, was considered a K-frame design. That design has the bridge resting on supports set in the ground, but it has no second support if they fail.

The state Department of Transportation has ordered five other bridges across the state with a similar design to be reviewed.

That design will be part of the federal investigation.

“The NTSB is evaluating the design of the bridge, its condition at the time of the collapse, its maintenance and rehabilitation history, and its inspection and load rating history,” the report said. “As the investigation progresses, the NTSB plans to conduct forensic examination of several of the bridge’s structural components.”

Advertise with us

Investigators also have recovered video from seven cameras that were on the bus, five showing an inside view, one showing a rear view from the curb side of the bus and the other facing forward. The initial review of the video “is consistent” with the initial review of bridge components, the report said, and a team of specialists will examine he video to see if anything else can be learned from it.

GangaRao Hota, an engineering professor and director of the Constructed Facilities Center at West Virginia University, said the bus video confirming that the collapse began at the west end of the bridge supports his belief that using wire cables on the west end became the bridge’s “Achilles’ heel.”

“I think that is what caused it [to collapse] if you ask me. That’s my guess,” he said Monday after seeing the NTSB report. “That must have been due to heavy duty corrosion and also because of a fairly high degree of fatigue. We call this ‘fatigue corrosion,’ which is more accelerating towards failure than just basic corrosion.”

The Post-Gazette previously reported that city documents showed that the city installed wire cable under the west end of the bridge some time prior to 2014 to replace the “tension” the original, failing X-shaped, steel bracing was supposed to provide.

The city had previously conducted a stability analysis and found that the  X-shaped, cross-bracing steel supports were “non-functional” and the bridge was relying on the wire cables to be “tight and fully engaged,” according to city documents.

Advertise with us

By September 2013, the cable wires had become loose and had to be tightened.

By late 2018, the original X-shaped steel support had corroded so badly it had detached from the bridge’s legs and had to be removed completely.

Mr. Hota found using cable wires to replace the steel X-framed support to be “odd” because steel frame legs “are also fracture critical members.”

“That is just common sense,” Mr. Hota said, because if one of those four legs failed, the bridge would collapse.

The bridge, owned by Pittsburgh, had been rated in poor condition since 2011, first due to deterioration with its superstructure and later additional problems with its deck. Its inspection schedule was ramped up from every other year to yearly after 2014, but it wasn’t scheduled for major repairs until at least 2027.

Advertise with us

City officials say they aren’t allowed to release inspection reports or discuss its maintenance history because of the federal investigation.

The bridge collapsed slowly in sections, which prevented vehicles from being thrown off violently or crushed in the rubble. The bus was trapped from the rear by another slab of the bridge when the piece it was on fell at about a 45-degree angle, preventing it from falling backwards.

Emergency crews were able to get the driver and two passengers off the bus using a ladder.

The Federal Highway Administration has awarded the state an emergency grant of $25.3 million to design and build a new bridge. PennDOT is leading that effort and has hired HDR Inc. to design the new structure and Swank Construction Co. to build it. They received no-bid contracts for the work so the contractor can build sections as they are designed.

The 497-foot bridge carried Forbes Avenue from Squirrel Hill to Point Breeze in Pittsburgh’s East End. President Joe Biden, who was scheduled to be in the Pittsburgh area that day to tout his infrastructure program, visited the scene to lend emphasis to the need for improvements.

Ed Blazina: eblaina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina. Sean D. Hamill: shamill@post-gazette.com or 412-263-2579 or Twitter @SeanDHamill.