It's not spring yet, but it is time for the first major disruption from the ongoing rehabilitation of the Neville Island Bridge on Interstate 79.

The southbound ramp from Route 65 to the interstate in Glenfield will close beginning at 9 a.m. Monday until early March, marking the start of a construction season that will see four full weekend closures on the southbound side of the interstate this year. The work is part of a three-year, $43 million project that will continue into the summer of 2023.

In addition to closing the southbound Route 65 ramps to I-79 in both directions, Trumbull Corp. also will close the ramp from Deer Run Road. Trumbull is the prime contractor for the Pennsylvania Department of Transportation project that began last year.

Closing the ramps will allow crews to also close the ramp acceleration lane and southbound shoulder on the bridge. They will install metal pans as part of the overhead suspension paint containment system, which PennDOT said has to be done during daylight hours for the safety of workers and motorists.

Advertise with us

The bridge crosses the Ohio River between Glenfield on one side and Neville and Robinson on the other side.

The posted detour for traffic on Route 65 and Deer Run Road directs motorists to take I-79 north one exit to Mt. Nebo, get off and then get back on heading south. Another alternative for motorists on Route 65 is to cross the Sewickley Bridge, turn left on Route 51 south through Coraopolis to I-79 south.

Off-duty police officers will be at various location along the detour route to kelp keep traffic moving.

PennDOT said the bridge will be fully closed in the southbound direction for four weekends during the construction season and the ramps will be closed again in the fall, but the dates haven’t been determined yet.

Crews closed the bridge northbound for four weekends last summer.

Advertise with us

The entire project includes structural steel repairs; full structure painting; bearing and deck joint replacements; deck repairs and overlays; bridge barrier repair; substructure concrete work; drainage improvements; concrete roadway reconstruction; guide rail replacement; and preservation work on four sign structures.

The project also will include preservation work on the I-79 bridge above Deer Run Road, north of the Neville Island Bridge.