The outbound traffic pattern on Route 28 near the Highland Park Bridge will change again Monday as part of the $47.3 million project to rebuild the interchange with the bridge.

Traffic already has been reduced to one northbound lane for several months. That will continue, but crews from Golden Triangle Construction will shift traffic from the left lane to the right lane beginning at 6 a.m.

That work is all part of the project to create two free-flowing lanes in each direction around the bridge. Right now, the approach toward the bridge has one lane and an exit lane, but when the project is finished there will be two lanes and an exit lane, eliminating a bottleneck at the interchange.

This year, crews are working mostly on the northbound lanes, with traffic limited to one 11-foot-wide lane. The northbound exit ramp from Route 28 to the bridge has been closed since mid-June, and traffic that normally crosses the bridge faces an extensive detour either through Sharpsburg or across the 61st Street Bridge.

Advertise with us

The ramp from Route 28 to the Highland Park Bridge and two lanes of traffic are scheduled to reopen Sept. 13.

Work next year is expected to be concentrated on the southbound lanes, which will face additional traffic restrictions.

The project also includes work to install traffic lights where Freeport Road traffic merges onto the bridge to head south, as well as on Freeport Road at the ramp just past Western Avenue in Aspinwall that takes traffic to a merge point on the bridge and then onto Route 28.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.