PennDOT announced that the ramp that carries traffic from northbound I-579 to Seventh Avenue, Downtown is expected to reopen Thursday morning, possibly at 8.
As part of the I-579 “Cap” Urban Connector project, the ramp was closed to traffic for nearly 700 days beginning in September 2019. The new structure is a park that will provide a direct connection between Downtown and the Hill District.
Remaining work on the project includes underdeck lighting installation, milling and paving operations, and installation of park items including sidewalks, artwork, and lighting. This work, and seeding and planting, will continue through November 2021. Restrictions on I-579, local roadways, and various ramps will continue through the remainder of the project.
Approximately 2,250 vehicles use the ramp each day.
The $29.34 million project, sponsored by the City of Pittsburgh and the Sports and Exhibition Authority, consists of the construction of a structure spanning I-579. In part, the Cap project will create a new three-acre greenspace which will include pedestrian pathways, bicycle routes, rain gardens for storm water management, and design elements from neighborhood artists.





Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.