Construction will alter traffic on Hulton Road

Starting Monday, drivers can expect traffic alterations on Hulton Road in Plum because of construction for the turnpike bridge. Also known as State Route 2058, Hulton Road will have flaggers posted between Eastern and Frankland avenues until July 2.

These flaggers will direct alternating single-lane traffic in both directions from 9 a.m. to 3 p.m. during weekdays. Crews will be preparing the road for later construction.

This later construction will occur between Eastern and Frankland avenues from July 7 through Aug. 9. Hulton Road will be closed completely between these dates. Construction crews are to work on upgrading the drainage and furthering other improvements of the road.

Advertise with us

The construction on Hulton Road is part of a larger future project to completely reconstruct the roadway between turnpike mileposts 49 to 53. An estimated $92 million will be spent to widen the existing mainline and replace bridges and overpasses over it.

The planned construction on Hulton Road is near milepost 49.53 of the turnpike.

A 14-mile detour will be posted directing traffic to:

Allegheny River Blvd. to

Coal Hollow Road to

Advertise with us

Frankstown Road to

Leechburg Road to

Unity Road and back onto Hulton Road.

Hannah Wyman: hwyman@post-gazette.com, 412-263-1255