Motorists in Pittsburgh’s Troy Hill neighborhood began using the new Lowrie Street Bridge over Rialto Street Friday.
Lowrie and Rialto streets had been closed in that area since July while A. Merante Contracting replaced bridge beams, deck, sidewalks and railings on the bridge as part of a $1.14 million project. A set of metal steps pedestrians use to get from Lowrie to Rialto were moved from one side of the bridge to the other so people won’t have to cross Rialto to get to the sidewalk.
The project had been scheduled to be finished by the end of the year, but delays pushed work into the winter season and crews had to wait for asphalt plants to open this month to pave the bridge deck.
Mayor Bill Peduto is expected to join neighborhood group Troy Hill Citizens for a ribbon-cutting ceremony and celebration of the bridge reopening at 12:30 p.m. Saturday.